• Refine Query
  • Source
  • Publication year
  • to
  • Language
  • 1
  • Tagged with
  • 1
  • 1
  • 1
  • 1
  • 1
  • 1
  • 1
  • 1
  • 1
  • 1
  • 1
  • About
  • The Global ETD Search service is a free service for researchers to find electronic theses and dissertations. This service is provided by the Networked Digital Library of Theses and Dissertations.
    Our metadata is collected from universities around the world. If you manage a university/consortium/country archive and want to be added, details can be found on the NDLTD website.
1

Achieving successful implementation of lean manufacturing control systems, to achieve world class status, at Ford Motor Componay of Southern Africa

Govender, Shawn Prakash January 2002 (has links)
Ford Motor Company embarked on a new engine programme, called the Rocam Engine Programme, in the year 2001. This engine was developed specifically for the European market. The customer demand rate was small initially, but ramped up slowly over time. During the low production volume period, this engine was introduced into the local market to test the publics’ response. The response was overwhelmingly positive. The local market grew considerably in a short space of time. During the same time-period, the European customer demand increased, unexpectedly, by approximately 60 percent. The additional production volume placed an enormous amount of pressure on the Engine Plant facility. Two of the production lines in particular, were taking huge strain. These lines were not producing the demand quantities, and the product quality levels were dropping quickly. The research project is based purely on the lean manufacturing principles and philosophies. The aim of the study is to identify the deficiencies on these two production lines, thereby allowing corrective action to be taken. The research methodology comprised of the following steps: · A literature study was performed to give the reader a better understanding of the principles and philosophies of lean manufacturing. · A second literature study was also performed to get a better understanding of the continuous improvement philosophies of lean manufacturing. · A current state map, which depicts the existing situation on the line, was developed for both production lines. The existing situation was then compared to the fundamental principles and philosophies of a lean manufacturer. In this way the deficiencies were highlighted to management. Several recommendations were made regarding the data obtained in the study. The key ones are as follows: · First-line management needs to be trained and coached into managing their business by using quality, cost and delivery as the key performance metrics. They also have to be trained in team dynamics. This will promote cross-functional brainstorming and problem solving sessions. · The accurate collection and processing of base-measurement data should be treated as cardinal, and road shows by production personnel should be presented every week to top management. This will ensure that data is regularly collected and corrective action is continually taken to improve the current situation. Operating personnel needs to be trained in this discipline. Management needs to be serious about implementing lean production principles by enforcing these road shows. · The objectives of Kaizen, production management and the supporting departments (including maintenance and MP&L) ought to be the same in the interest of maximum productivity i.e. leaning towards world class. · First-line management must develop formal structured plans that will rectify the current on-line situation. Plans must include medium to longterm objective setting. Senior management need to coach the first-line management in this discipline. · Few production systems can be implemented without the necessary infrastructure conducive to supporting it. An infrastructure where production gets involved and takes ownership (policy deployment with regards to lines of communication and responsibility between Area Managers, Production Coordinators, Team Leaders and contractors) is what is required. Lean manufacturing deficiencies on the two production lines have been identified. A detailed implementation plan, which needs to be developed by the Ford Production System department, needs to be given to management. This plan needs to address the identified deficiencies in a timely manner that will assist in the Engine Plant meeting their production targets.

Page generated in 0.0661 seconds