Spelling suggestions: "subject:"2around anchor"" "subject:"2around anchored""
1 |
Studies of the interface resistance of soil nailsStanding, James R. January 1997 (has links)
No description available.
|
2 |
The behaviour of ground anchors in sandTsangarides, Stelios Nicolaou January 1978 (has links)
This thesis includes experimental and theoretical work performed to investigate the behaviour of ground anchors in sand. The anchor footing used was a circular plate connected to a tie rod. The experimental work was carried out by installing the anchor in a l830mm x 1830mm x l220mm deep tank containing dry sand. The sand sample was prepared by using a vibrator fixed to the bottom of the tank. The anchor was pulled out at a constant rate of strain and the load-displacement curve was recorded on a plotter. The vibration of the tank was defined by deter.mining the acceleratton and amplitude of the motion in the horizontal and vertical directions. A density tube and a hydraulic gauge were designed to investigate the distribution of stresses in sand. The variation of the vibration time, the constant rate of strain, the shaf V plate diameter, the plate thickness/plate diameter, and the boundary distance with the load-displacement curve were also investigated. The load-displacement curve of different diameter plates embedded at various depths for different times of vibration were recorded. To investigate the behaviour of ground anchors theoretically, the finite element technique was used and a computer progra~ developed. A linear stress-strain relationship was used to predj.ct and investigate the behaviour of the anchor. A non-linear stress-strain relationship and a failure criterion were also used to predict the load-displacement curve of the vertical anchor. The effect of the parameters which were investigated experimentally were also examined. The distribution of the load on the anchor plate and the extent of the failure zone were plotted. The predicted and experimental results in this thesis were compared with laboratory and field results obtained by previous researchers.
|
3 |
PERFORMANCE OF TWO TIEBACK WALLS AND ROCK ANCHORS IN A SHALE STRATUMRomana Giraldo, Jorge Octavio 01 January 2018 (has links)
Tieback walls are typically design based on predetermined pressure distribution; however, these pressures were proposed based on performance of excavations. For retaining walls used in slope remediation, the application of these pressures might not be adequate; the construction procedure; therefore, a different response of the wall is expected. This document, presents the performance of two tieback walls installed in a shale stratum. Monitored responses is correlated with construction activities; these activates implied excavation and backfilling in both of the tieback walls. In addition, this research shows a numerical procedure to evaluate the anchor capacity based on the t- z approach. Finally, this study introduces an empirical method to estimate lateral wall deformation profiles and internal bending moments along a retaining wall installed in a clay stratum.
|
4 |
Založení stavby River Garden III v Praze / Foundation design of River Garden III in PragueMalinský, Martin January 2015 (has links)
The topic of this master's thesis are the design of ensuring foundation pit and foundation of administrative building in Prague. In the vicinity of foundation pit is situated the river Vltava, which directly influences the ground water level at the job site. During construction, it is necessary to envisage the possibility of occurrence of the old building structures of docks.
|
5 |
Stavebně technologický projekt přístavby objektu Nejvyššího soudu ČR v Brně / Construction technology project of extension of the Supreme Court building in BrnoConík, Šimon Unknown Date (has links)
Theme of the diploma thesis is a construction technology project extension of the building of the Supreme Court of the Czech Republic in Brno. The content of the diploma thesis is the study of the main technological stages of the main building, solution of wider transport relations with a focus on building supply, objects schedule, time schedule of the main building. The work also includes the project of construction site equipment, design of the main construction machines and mechanisms, technological regulations for special foundations and rough construction, which are supplemented by control and test plans and a plan for securing material resources. As part of other assignments, As part of other assignments, I process occupational health and safety, ecology and environmental protection for selected construction processes, itemized budget for special foundation and rough construction
|
Page generated in 0.0428 seconds