Incumplimiento de plazo y costo por la deficiente elaboración de expedientes técnicos, al no utilizar herramientas de la metodología BIM, en el sector público de la región Arequipa. Caso de estudio: Construcción de las Escuelas Profesionales de Ciencias de la Computación e Ingeniería de Telecomunicaciones, distrito, provincia y región Arequipa / Failure to comply with the deadline and cost due to the deficient preparation of technical files, by not using bim methodology tools, in the public sector of the arequipa region. case study: construction of the professional schools of computer science and telecommunications engineering, district, province and region of arequipa

En un informe del Ministerio de Economía y Finanzas MEF del año 2020, se indica que 534 inversiones en la Cartera de Infraestructura Educativa recibieron transferencias para la ejecución de obras. El 87% de estas inversiones presentaron interferencias por deficiencias en el Expediente Técnico, lo cual originó que S/ 447 millones fueran devueltos al Tesoro Público. Ello, evidencia que, el aparato gubernamental realiza una deficiente gestión de las inversiones en los proyectos sociales y de infraestructura.

Por lo tanto, es importante enfocar esfuerzos en realizar los estudios previos adecuados para el proyecto. La optimización de los recursos y una mayor eficiencia en la elaboración del Expediente Técnico, disminuirán los cambios inesperados durante la ejecución y redundará en un mayor beneficio para el usuario final.

El presente trabajo de investigación desarrollará pautas para la elaboración de un Expediente Técnico más eficiente y consistente, valiéndonos de herramientas de la Metodología BIM, teniendo en cuenta la normatividad legal que promueve su uso.

Para lograr una mayor eficiencia en la elaboración del Expediente Técnico, se propone un entorno colaborativo, en el que se programarán reuniones con la participación de todo el equipo del proyecto, se intercambiará información, se resolverán las deficiencias detectadas y finalmente se consolidará la información de los modelos 3D generados por los diversos especialistas, surgiendo el modelo BIM integrado. Con esta información se podrán elaborar todos los documentos que forman parte del Expediente Técnico, conformándose un documento más eficiente y consistente.

Dentro del contenido de este trabajo, se incluye un Análisis del Impacto en el Plazo y Costo del proyecto como producto de las deficiencias detectadas en el Expediente Técnico del Caso de Estudio. Y al final, se incluirá una propuesta de mejora en el proceso de elaboración del Expediente Técnico. / In a report from the Ministry of Economy and Finance MEF for the year 2020, it is indicated that 534 Investments in the Educational Infrastructure Portfolio received transfers for the execution of works. 87% of these investments presented interferences due to deficiencies in the Technical File, which caused S/ 447 million to be returned to the Public Treasury. This shows that the government apparatus performs a deficient management of investments in social and infrastructure projects.

Therefore, it is important to focus efforts on conducting the appropriate preliminary studies for the project. The optimization of resources and greater efficiency in the preparation of the Technical File will reduce unexpected changes during execution and will result in greater benefit for the end user.

This research work will develop guidelines for the elaboration of a more efficient and consistent Technical File, using the tools of the BIM methodology, acording to the current legal regulations.

To achieve greater efficiency in the preparation of the Technical File, a collaborative process is proposed, in which meetings will be scheduled with the participation of the entire project team, information will be exchanged, the deficiencies detected will be resolved and finally the information on the 3D models generated by the various specialists, emerging the integrated BIM model. With this information, all the documents that are part of the Technical File can be prepared, forming a more efficient and consistent document.

Within the content of this work, an Analysis of the Impact on the Term and Cost of the project is included as a result of the deficiencies detected in the Technical File of the Case Study. And at the end, an Improvement Proposal will be included in the process of preparing the Technical File. / Trabajo de investigación

Identiferoai:union.ndltd.org:PERUUPC/oai:repositorioacademico.upc.edu.pe:10757/659319
Date13 September 2021
CreatorsApaza Mango, Victor Angel, Silva Escalante, Hernán Juan, Tagle Arizaga, Amaral Francisco
ContributorsTalavera Velásquez, Oscar Reynaldo
PublisherUniversidad Peruana de Ciencias Aplicadas (UPC), PE
Source SetsUniversidad Peruana de Ciencias Aplicadas (UPC)
LanguageSpanish
Detected LanguageEnglish
Typeinfo:eu-repo/semantics/masterThesis
Formatapplication/pdf, application/epub, application/msword
SourceUniversidad Peruana de Ciencias Aplicadas (UPC), Repositorio Académico - UPC
Rightsinfo:eu-repo/semantics/openAccess, Attribution-NonCommercial-ShareAlike 4.0 International, http://creativecommons.org/licenses/by-nc-sa/4.0/

Page generated in 0.0021 seconds