關鍵鏈專案管理中多重專案排程與控制之緩衝管理方法研究 / Buffer Management for Multi Project Scheduling and Control in Critical Chain Project Management

無 / Critical Chain Project Management (CCPM) has merged in last few years as a novel approach for managing projects. While there were many previous researches studied CCPM concerning with single project management, but CCPM multi project management was hardly paid attention, especially capacity-constraint buffer sizing approach. However, there were some research papers which examined and illustrated CCPM under multi-project environment; those papers assumed all the subprojects were identical. Despite the fact that such situation is impractical.
The purpose of this dissertation is to compare Cut and paste method (C&PM) with Root square error method (RSEM) for applying in project buffer, feeding buffer and capacity-constraint buffer sizing and to change some subproject parameters which make an impact on the project schedule for multi-project scheduling.

Keywords: Critical chain project management, Multi Project Scheduling, Buffer Management, Capacity constraint buffer, Buffer sizing method.

Identiferoai:union.ndltd.org:CHENGCHI/G0093356042
Creators吳敬賢, Nuntasukasame, Noppadon
Publisher國立政治大學
Source SetsNational Chengchi University Libraries
Language英文
Detected LanguageEnglish
Typetext
RightsCopyright © nccu library on behalf of the copyright holders

Page generated in 0.0021 seconds