Estudo dos fatores do planejamento financeiro de curto prazo: o caso de uma empresa do setor de construção civil

Submitted by Fabio Sobreira Campos da Costa (fabio.sobreira@ufpe.br) on 2016-03-31T14:02:20Z
No. of bitstreams: 2
license_rdf: 1232 bytes, checksum: 66e71c371cc565284e70f40736c94386 (MD5)
Dissertação_2014_12_19_Michelle Hofmann Dourado.pdf: 6045933 bytes, checksum: b87585642739965e8958d3741471cc9a (MD5) / Made available in DSpace on 2016-03-31T14:02:20Z (GMT). No. of bitstreams: 2
license_rdf: 1232 bytes, checksum: 66e71c371cc565284e70f40736c94386 (MD5)
Dissertação_2014_12_19_Michelle Hofmann Dourado.pdf: 6045933 bytes, checksum: b87585642739965e8958d3741471cc9a (MD5)
Previous issue date: 2014-12-19 / O objetivo deste estudo foi identificar e analisar os possíveis fatores que podem promover
alterações nos fluxos de caixa planejados de empreendimentos habitacionais de uma
construtora de grande porte em Recife. Trata-se de um estudo de caso qualitativo onde foram
comparados e analisados os fluxos de caixa previstos e realizados de três empreendimentos
habitacionais, concluídos no ano de 2013, escolhidos propositalmente para análise da
metodologia utilizada em suas projeções. Os dados foram coletados através de entrevistas e
pesquisa documental e por meio deles foi possível concluir que o método de projeção
utilizado gerou grandes distorções entre os fluxos de caixa planejados e realizados destes
empreendimentos. Dentre estas distorções foi possível destacar os desvios causados pela
utilização da curva de evolução física de obra para projeção dos desembolsos referentes ao
custo de obra, os desvios relacionados a falha na projeção dos repasses de clientes e o efeito
da complexidade, singularidade e prazo dos projetos nestas projeções. / The objective of this study was to identify and analyze the possible factors that may cause
changes in planned cash flows of housing developments from a large construction company in
Recife. This is a qualitative case study that compared and analyzed estimated and realized
cash flows of tree housing projects completed in 2013. These projects where purposely
selected to have their projections methodology analyzed. The Data for this study was obtained
via personal interviews and Documentary research. Through the data analysis it was possible
to conclude that the utilized projection method generated major distortions between planned
and realized cash flows for these businesses. Among these distortions it was possible to
highlight the deviations caused by the use of physical evolution curve of construction for
disbursements projections related to the cost of building, the deviations related to failure in
the projection of customer transfers, and the effects of complexity, uniqueness and term of
projects in these projections.

Identiferoai:union.ndltd.org:IBICT/oai:repositorio.ufpe.br:123456789/16231
Date19 December 2014
CreatorsDOURADO, Michelle Hofmann
Contributorshttp://lattes.cnpq.br/5657418279526928, SANTOS, Joséte Florencio dos
PublisherUniversidade Federal de Pernambuco, Programa de Pos Graduacao em Administracao, UFPE, Brasil
Source SetsIBICT Brazilian ETDs
LanguageBreton
Detected LanguagePortuguese
Typeinfo:eu-repo/semantics/publishedVersion, info:eu-repo/semantics/masterThesis
Sourcereponame:Repositório Institucional da UFPE, instname:Universidade Federal de Pernambuco, instacron:UFPE
RightsAttribution-NonCommercial-NoDerivs 3.0 Brazil, http://creativecommons.org/licenses/by-nc-nd/3.0/br/, info:eu-repo/semantics/openAccess

Page generated in 0.0018 seconds