Implementación del sistema Last Planner para la mejora de la etapa de planeación en la construcción de muros de contención, caso región Cusco, 2021 / Implementation of the Last Planner system to improve the planning stage in the construction of retaining walls, Cusco region, 2021

El presente trabajo de investigación tiene la finalidad de implementar el Sistema Last Planner como parte de la etapa de planeamiento del expediente técnico de una obra piloto ejecutada bajo administración directa del Gobierno Regional de Cusco. Con la finalidad de gestionar las restricciones identificadas durante la ejecución de obra.
Se obtuvo que las principales restricciones fueron la responsabilidad de los ejecutores de obra y a su vez agentes externos de los que depende el avance, los tiempos previstos en el expediente técnico no son flexibles ante cambios o imprevistos y finalmente que los proveedores no cumplen la entrega puntual de bienes y servicios.
El contexto se planteó desde las definiciones y normas que rigen al gobierno regional, su sistema de funcionamiento a través de unidades ejecutoras y finalmente a las obras ejecutadas bajo administración directa de la sede central del gobierno regional de donde se seleccionó una obra piloto que culmino su ejecución recientemente para recoger las restricciones y problemas que tuvo.
Luego aplicar el sistema Last Planner al expediente técnico de la obra piloto se pudo comparar con el proyecto inicial donde finalmente se concluyó que implementar el Last Planner logra un mejor desempeño al tener herramientas suficientes para garantizar el cumplimiento de las asignaciones en el tiempo establecido, lo que se refleja en menos inventarios intermedios estancados y mejor optimización del uso de mano de obra. / The purpose of this investigation work is to implement the Last Planner System as part of the planning stage of the technical file of a pilot project executed under the direct administration of the Regional Government of Cusco. To manage the restrictions identified during the execution of the work.
It was found that the main restrictions were the responsibility of the work executors and external agents on which progress depends, the times provided in the technical dossier are not flexible to changes or unforeseen events and finally that suppliers do not meet the timely delivery of goods and services.
The context was approached from the definitions and norms that govern the regional government, its system of operation through executing units and finally to the works executed under direct administration of the regional government headquarters, from which a pilot work was selected that recently finished its execution to collect the restrictions and problems it had.
After applying the Last Planner system to the technical file of the pilot project, it was possible to compare it with the initial project where it was finally concluded that implementing the Last Planner system achieves better performance by having sufficient tools to guarantee the fulfillment of the assignments in the established time, which is reflected in less intermediate inventories stagnant and better optimization of the use of labor. / Tesis

Identiferoai:union.ndltd.org:PERUUPC/oai:repositorioacademico.upc.edu.pe:10757/659150
Date25 November 2021
CreatorsMejía Olivera, Brandon David, Chavez Palomino, Leonardo German
ContributorsTalavera Velásquez, Oscar Reynaldo
PublisherUniversidad Peruana de Ciencias Aplicadas (UPC), PE
Source SetsUniversidad Peruana de Ciencias Aplicadas (UPC)
LanguageSpanish
Detected LanguageEnglish
Typeinfo:eu-repo/semantics/masterThesis
Formatapplication/pdf, application/epub, application/msword
SourceUniversidad Peruana de Ciencias Aplicadas (UPC), Repositorio Académico - UPC
Rightsinfo:eu-repo/semantics/openAccess, Attribution-NonCommercial-ShareAlike 4.0 International, http://creativecommons.org/licenses/by-nc-sa/4.0/

Page generated in 0.0022 seconds