Automating Indoor Construction Progress Monitoring: Technical Challenges, Industry Perceptions, and Low-cost Implementation

Abstract

dc:description.abstract

Construction projects frequently suffer delays and cost overruns because progress information is fragmented, slow to obtain, and difficult to convert into timely actions. Automated construction progress monitoring (ACPM) seeks to address this gap, yet most studies emphasise sensing and reporting while paying less attention to low-cost deployment and to schedule optimisation once progress is known. This thesis investigates a practical, affordable pathway for indoor construction progress monitoring (ICPM) that closes the loop from sensing to scheduling. This study explores the following objectives: 1) summarising the technical challenges across the ICPM pipeline and assess their impacts; 2) identifying professionals’ perceptions of ACPM adoption in practical construction projects; 3) developing a low-cost 3D Light Detection and Ranging (LiDAR) and computer vision method for detecting interior construction structures; and 4) utilising reinforcement learning (RL) techniques to solve Multi-Skill Resource Constrained Project Scheduling Problem (MSRCPSP) and comparing algorithmic performance To achieve the research objectives, several methods are adopted to analyse the collected primary and secondary data in this study. First, a structured systematic review is performed to identify and summarise the technical and organisational barriers to ICPM. The Preferred Reporting Items for Systematic Reviews and Meta-Analyses (PRISMA) framework is utilised for filtering and selecting literature. The study systematically identifies stage-specific obstacles, pinpointing 11 major challenges and 41 sub-challenges. Among these, the data collection phase emerges as both the most challenge-intensive stage. Furthermore, challenges arising in other phases also propagate along the workflow, collectively contributing to a decline in overall automation performance. Moreover, a Q-methodology study, organised with an extended Unified Theory of Acceptance and Use of Technology (UTAUT) framework, surfaces four viewpoints among practitioners: advocates who actively endorse ACPM, sceptics who question its promised cost savings, negativists who show little enthusiasm, and realists who remain cautious about its technological maturity. The groups shared common concerns about resistance to organisational change and additional costs, tempered by a broad acknowledgment that ACPM can strengthen project tracking and visibility. In addition, a structural detection system was developed using commercial iOS LiDAR and geometry-based deep network (VoteNet) to classify interior partition wall states (e.g., framing structures, insulation layers, drywall). The results achieved accuracy comparable to existing computer vision–based drywall detectors, underscoring the method’s promise for construction element recognition. In addition, the study demonstrates the practicality of leveraging the iOS built-in LiDAR scanner for element detection and contributes a benchmark dataset specifically for interior drywall, facilitating future evaluation and comparison. Yet, the structure identification achieved here only provides visualisation and report of the as-built progress information, which might not match with the original schedule plan. To punctually respond to any delayed progress, approaches for solving scheduling problems should be looked into. Therefore, the reinforcement learning (RL) and Deep RL (DRL) techniques are employed to design a learning-based scheduler for the Multi-Skill Resource-Constrained Project Scheduling Problem (MSRCPSP). The performance of the DRL-based optimiser is compared against the widely used heuristics and metaheuristics like genetic algorithm, particle swarm optimisation, and the black-winged kite algorithm. The results show that learning-based methods, particularly Proximal Policy Optimisation, consistently produce optimal or near-optimal schedules and achieve shorter makespans than heuristic and metaheuristic baselines. Together, the contributions demonstrate an accessible “hear-sense-decide” loop: challenges summarised from the research field and opinions from industry experts drive more targeted development towards a low-cost and accessible direction; routine, low-overhead scanning generates trustworthy progress data; this data drives adaptive scheduling in response to actual site conditions; and the combined workflow reduces schedule risk while easing adoption through familiar tools, particularly for small and medium contractors. It also points to governance needs, including privacy, retention, and interoperability with BIM/IFC and ISO standards, so that routine spatial data collection can strengthen the project information ecosystem. Overall, this study advances both the theoretical and practical aspects of ACPM by demonstrating that low-cost sensing and RL-based scheduling can be combined to improve time and cost performance in residential and commercial building projects.

Degree

thesis:*
College dc:contributor.school
School of Architecture and Civil Engineering
Year dc:date.issued
2025

Author and committee

dc:creator, dc:contributor.*
Author dc:creator
  • Zhang, Yanquan
Advisors dc:contributor.advisor
  • Chang, Ruidong
  • Omrany, Hossein

Subjects

dc:subject × 6

Rights

Language dc:language.iso
en

Identifiers

dc:identifier.*
Handle dc:identifier.uri
https://hdl.handle.net/2440/152808

Chain of custody

source
Harvested from
University of Adelaide
Base URL
digital.library.adelaide.edu.au/server/oai/request
Last updated
2026-11-19
Source record
OAI-PMH GetRecord
citation

Zhang, Yanquan. Automating Indoor Construction Progress Monitoring: Technical Challenges, Industry Perceptions, and Low-cost Implementation. 2025. https://hdl.handle.net/2440/152808