Advancing Construction Planning in Remote Regions: A Stochastic Time-Window Framework for Schedule and Cost Efficiency

Abstract

dc:description.abstract

Construction planning in remote regions is significantly challenged by stochastic time-window constraints induced by environmental and logistical factors. These constraints, such as limited access (e.g., no physical road), unpredictable weather (e.g., typhoons, blizzards, shifting freeze-thaw cycles, sand storms), and regulatory nature-based restrictions (e.g., season-based ecosystem protection regulations), introduce uncertainties that traditional construction planning methods like the Critical Path Method or Time-Cost Trade-off analysis are not designed to accommodate effectively. As a result, plans generated by such techniques are often flawed and infeasible, leading to persistent delays and cost overruns in projects undertaken in harsh, remote environments. Addressing these challenges is critical for infrastructure development, which has a socio-economic impact on remote communities. Furthermore, in the mining industry, often involving distant operations, the efficiency and feasibility of natural resource extraction can also be impacted by environmental and logistical constraints. Evidently, attempting the execution of construction projects in such settings almost certainly involves schedule delays and budget overruns. As traditional planning methods fall short, the demand for a robust strategy to tackle environmental uncertainties is especially evident in the context of climate change and unpredictable natural phenomena. A stochastic time-window framework has been developed to enhance construction planning and scheduling in remote settings. This framework integrates environment-induced constraints into the scheduling process, optimizes the selection of alternative execution methods for environment-sensitive activities, and quantifies the impact of stochastic time windows on project duration and total cost, thus addressing the shortcomings of conventional planning and cost optimization techniques. Initially, a Time-Window planning method was formulated to incorporate environmental constraints, validated via a case study of a river-crossing bridge in a remote northern region of Canada. Subsequently, a quantitative optimization framework was developed, employing enumerated simulation and an analytical reward function ranking alternative execution methods and crew configurations. Finally, a simulation-based approach utilizing the Monte Carlo method and historical meteorological and winter road access data was implemented to model the stochastic nature of environmental time windows for a project situated in northern Canada. The findings of this dissertation indicate that the proposed framework substantially improves schedule reliability over traditional methods in the settings of logistically complex and climate-sensitive regions. The Time-Window planning method ensures practical construction scheduling under environmental constraints, while the time-cost optimization framework identifies effective execution alternatives in parallel. Finally, the stochastic simulation of weather-related constraints reveals a likelihood of delays and budget overruns when compared to baseline estimates based on average records. These findings suggest that the stochastic time-window framework can be adopted as a valuable tool by construction planners in remote regions. By enabling more accurate scheduling, cost management, and risk budgeting, the framework enhances the feasibility of construction projects in geographically and environmentally challenging areas and advances the field of construction engineering and management.

Degree

thesis:*
Name thesis:degree_name
Doctor of Philosophy
Level thesis:degree_level
Doctoral
Discipline thesis:degree_discipline
Construction Engineering and Management
Grantor
University of Alberta
Year dc:date.issued
2025

Author and committee

dc:creator, dc:contributor.*
Author dc:creator
  • Naumets, Serhii
Advisor dc:contributor.advisor
  • Lu, Ming (Civil and Environmental Engineering)

Subjects

dc:subject × 5

Rights

dc:rights
Statement dc:rights
  • This thesis is made available by the University of Alberta Library with permission of the copyright owner solely for non-commercial purposes. This thesis, or any portion thereof, may not otherwise be copied or reproduced without the written consent of the copyright owner, except to the extent permitted by Canadian copyright law.
Language dc:language.iso
en

Identifiers

dc:identifier.*
DOI dc:identifier.doi
https://doi.org/10.7939/83219

Chain of custody

source
Harvested from
University of Alberta
Base URL
era.library.ualberta.ca/oai
Last updated
2026-11-26
Source record
OAI-PMH GetRecord
citation

Naumets, Serhii. Advancing Construction Planning in Remote Regions: A Stochastic Time-Window Framework for Schedule and Cost Efficiency. Doctoral thesis, University of Alberta, 2025. https://doi.org/10.7939/83219