Advanced Time-Series Forecasting of Construction Project Cost Estimate At Completion (EAC) Incorporating Inefficiency Impacts

Abstract

dc:description.abstract

Construction projects are highly susceptible to inefficiencies arising from factors such as adverse weather conditions and rework, both of which can significantly distort productivity, schedules, and cost forecasts. Traditional Earned Value Management (EVM) methods, while widely adopted, rely primarily on historical performance indices and often fail to account for such external disruptions. This limitation reduces their ability to provide accurate forward-looking estimates, particularly for projects exposed to high uncertainty. This research addresses these shortcomings by developing a data-driven forecasting framework that integrates inefficiency measures into advanced time-series models. A comprehensive Earned Value data collection system was established for a steel erection project in Saskatchewan, Canada, including detailed records of actual and planned man-hours, as well as categorized inefficiencies. Among these, weather impacts and rework were identified as the two most dominant sources of productivity loss. These inefficiencies were quantified through the Weather Impact Ratio (WIR) and Rework Impact Ratio (RIR), which normalized man-hour losses relative to available resources. To forecast future inefficiencies, a non-parametric weather generator was created to simulate temperature and wind speed exceedances, which were then linked to WIR through polynomial regression. For RIR, polynomial trend fitting combined with probabilistic residual modeling was applied, with the lognormal distribution providing the best fit according to Kolmogorov–Smirnov test results. These stochastic simulations produced probabilistic forecasts of WIR and RIR, which were then incorporated as exogenous variables in ARIMAX models for key EVM indices including the Cost Performance Index (CPI) and Schedule Performance Index (SPI). The ARIMAX forecasts demonstrated superior accuracy compared to both simple ARIMA models and traditional EVM-based formulas. Forecast errors were consistently lower, with ARIMAX-based Integrated Estimates at Completion (IEAC) achieving a Mean Absolute Percentage Error (MAPE) of 3.9%, compared to 8.0% for ARIMA and over 18% for conventional CPI-based methods. The results confirmed that incorporating inefficiency-based predictors significantly improves the accuracy and robustness of project cost forecasts, while also offering probabilistic ranges that better reflect the uncertainty inherent in construction projects. This study makes contributions both to academic literature and to industry practice. It introduces a practical approach for quantifying and forecasting inefficiency impacts, demonstrates the value of integrating exogenous drivers into time-series forecasting, and develops graphical user interfaces to make the models accessible to practitioners. The findings suggest that by explicitly modeling the effects of weather and rework, project managers can achieve more reliable performance forecasts and enhance decision-making in dynamic project environments.

Degree

thesis:*
Name thesis:degree_name
Master of Science
Level thesis:degree_level
Master's
Discipline thesis:degree_discipline
Construction Engineering and Management
Grantor
University of Alberta
Year dc:date.issued
2026

Author and committee

dc:creator, dc:contributor.*
Author dc:creator
  • Hamza, Ameer
Advisors dc:contributor.advisor
  • Hammad, Ahmed (Civil and Environmental Engineering)
  • Mohamed, Yasser (Civil and Environmental Engineering)

Subjects

dc:subject × 8

Rights

dc:rights
Statement dc:rights
  • This thesis is made available by the University of Alberta Library with permission of the copyright owner solely for non-commercial purposes. This thesis, or any portion thereof, may not otherwise be copied or reproduced without the written consent of the copyright owner, except to the extent permitted by Canadian copyright law.
Language dc:language.iso
en

Identifiers

dc:identifier.*
DOI dc:identifier.doi
https://doi.org/10.7939/83988

Chain of custody

source
Harvested from
University of Alberta
Base URL
era.library.ualberta.ca/oai
Last updated
2026-11-26
Source record
OAI-PMH GetRecord
citation

Hamza, Ameer. Advanced Time-Series Forecasting of Construction Project Cost Estimate At Completion (EAC) Incorporating Inefficiency Impacts. Master's thesis, University of Alberta, 2026. https://doi.org/10.7939/83988