Integer-Programming-Assisted Path-Float-Based Method for Time-Cost Tradeoff Optimization in Project Planning

Abstract

dc:description.abstract

In theory, time-cost tradeoff (TCT) optimization is a classic planning problem appealing to construction management; yet, existing analytical methods are found inadequate to make a significant impact in practice. Heuristic methods lack a theoretical basis to ensure arriving at optimum solutions in solving specific problems; on the other hand, mathematical programming requires cumbersome, complicated formulation. This study proposes a new algorithm for TCT optimization that takes advantage of a path-float based scheduling technique and integer programming (IP). The project duration can be shortened in each iteration based on path lengths; while IP is nested to inform on which activities on the critical path(s) to shorten by how long duration. The new TCT optimization approach streamlines critical path analysis in each cycle by elimination of backward pass and finds optimal or near optimal solutions in terms of lowest project cost or shortest project duration. Since only a part of the network (critical paths) is modelled in IP formulation in each intermediate cycle, the complexity of IP formulation plus the search space is substantially reduced. Case studies are used to verify the proposed method and demonstrate its application. The proposed method can be automated to tackle large project networks commonly encountered in (1) project planning and scheduling and (2) acceleration planning and workface planning in construction management.

Degree

thesis:*
Name thesis:degree_name
Master of Science
Level thesis:degree_level
Master's
Discipline thesis:degree_discipline
Construction Engineering and Management
Grantor
University of Alberta
Year dc:date.issued
2019

Author and committee

dc:creator, dc:contributor.*
Author dc:creator
  • Nasiri,Sasan
Advisor dc:contributor.advisor
  • Lu, Ming (Civil and Environmental Engineering)

Subjects

dc:subject × 6

Rights

dc:rights
Statement dc:rights
  • Permission is hereby granted to the University of Alberta Libraries to reproduce single copies of this thesis and to lend or sell such copies for private, scholarly or scientific research purposes only. Where the thesis is converted to, or otherwise made available in digital form, the University of Alberta will advise potential users of the thesis of these terms. The author reserves all other publication and other rights in association with the copyright in the thesis and, except as herein before provided, neither the thesis nor any substantial portion thereof may be printed or otherwise reproduced in any material form whatsoever without the author's prior written permission.
Language dc:language.iso
en

Identifiers

dc:identifier.*
DOI dc:identifier.doi
https://doi.org/10.7939/r3-0fr9-dp98

Chain of custody

source
Harvested from
University of Alberta
Base URL
era.library.ualberta.ca/oai
Last updated
2026-11-26
Source record
OAI-PMH GetRecord
citation

Nasiri,Sasan. Integer-Programming-Assisted Path-Float-Based Method for Time-Cost Tradeoff Optimization in Project Planning. Master's thesis, University of Alberta, 2019. https://doi.org/10.7939/r3-0fr9-dp98