Automated Planning and Scheduling for Industrial Construction Processes

Abstract

dc:description.abstract

Cost overrun and schedule slippage are common problems for mega industrial construction projects. Lack of effective planning and scheduling tools is identified as a major contributing factor to poor project performance. Planning and scheduling tools should be custom designed to address the characteristics of mage industrial projects: unique components, modularized execution strategy and its extremely accelerated project delivery. The main objective of this research is to investigate and develop automated solutions for planning and scheduling two essential stages of mega industrial projects, shop fabrication and on-site construction. This research explores use of discrete event simulation (DES) to automate scheduling of shop fabrication and on-site construction processes. For industrial fabrication shops, a new simulation structuring methodology is developed to address the complex routing issue. Following this methodology, a simulation model is developed for pipe spool fabrication shops, which performs scheduling for shop operations, and mainly evaluates the impact of fabrication sequence on the spool cycle time. For site construction, a time-stepped simulation framework is developed to address congestion and dynamic resource allocation issue. For a real-life industrial construction case, this framework returns a schedule that has 12% shorter duration than those generated from Microsoft Project and Primavera P6. The research investigates use of domain-independent Artificial Intelligence (AI) planning to automate the sequence planing for pipe spool fabrication and on-site module installation. Experiment results show that AI planning is not suitable for sequencing spool fabrication due to the limited parsing capability of existing AI planners. However, AI planning is efficient to identify feasible sequence plans for module installation based on the current module availability and installation status. The research finds Dynamic Programming (DP) is suitable to sequence pipe spool fabrication. A DP algorithm is developed to automatically identify the optimal sequence in terms of the minimum position welds. Simulation experiments were conducted with 29 real-life spools to quantify the performance improvement obtained from the DP algorithm. Results showes that by using the DP algorithm, there is a 45% reduction in the number of position welds, which is translated to a reduction in the total cycle time, ranging from 4.8% to 12%.

Degree

thesis:*
Name thesis:degree_name
Doctor of Philosophy
Level thesis:degree_level
Doctoral
Discipline thesis:degree_discipline
Construction Engineering and Management
Grantor
University of Alberta
Year dc:date.issued
2013

Author and committee

dc:creator, dc:contributor.*
Author dc:creator
  • Hu, Di
Advisor dc:contributor.advisor
  • Yasser Mohamed (Civil and Environmental Engineering)

Subjects

dc:subject × 7

Rights

dc:rights
Statement dc:rights
  • This thesis is made available by the University of Alberta Libraries with permission of the copyright owner solely for non-commercial purposes. This thesis, or any portion thereof, may not otherwise be copied or reproduced without the written consent of the copyright owner, except to the extent permitted by Canadian copyright law.
Language dc:language.iso
en

Identifiers

dc:identifier.*
DOI dc:identifier.doi
https://doi.org/10.7939/R3V88D

Chain of custody

source
Harvested from
University of Alberta
Base URL
era.library.ualberta.ca/oai
Last updated
2026-11-26
Source record
OAI-PMH GetRecord
citation

Hu, Di. Automated Planning and Scheduling for Industrial Construction Processes. Doctoral thesis, University of Alberta, 2013. https://doi.org/10.7939/R3V88D