Instance-Based Model for Predicting Total Fabrication Duration of Industrial Pipe Spools

Abstract

dc:description.abstract

Industrial fabrication for modular installations has its own set of challenges that combine the environments of industrial manufacturing and off-site construction. This hybrid execution strategy means that fabricators need to look at both fields and adopt the best tools and techniques. This thesis presents an investigation into the improvement of delivery time estimates of industrial fabrication of a pipe spool fabrication shop in Alberta. The main contribution of the work is in the area of predicting the total fabrication duration to be expected in order to assist fabrication shop management in planning for appropriate workforce availability and material delivery date requirements. In order to address the objective of improving the prediction of fabrication durations, the spool manufacturing process has been modelled for simulation. However, the data required to validate this model was found to be time-consuming and cumbersome to capture at the required level of details. Alternatively, the development of a data-driven knowledge discovery experiment was pursued. The approach employed was to utilize the fabrication information that was already being captured by the manufacturing facility and evaluate it using instance-based classification. In addition, an effort towards the integration of manufacturing tracking and scheduling estimating is presented. This part of the work will ensure that the schedule is not consulted only at the beginning of a project, but throughout its completion. Updating a schedule with live fabrication progress data will allow production managers to update their completion date estimates and adjust the manufacturing plans to reflect existing issues such as material delivery and labor shortages or performance.

Degree

thesis:*
Name thesis:degree_name
Master of Science
Level thesis:degree_level
Master's
Discipline thesis:degree_discipline
Construction Engineering and Management
Grantor
University of Alberta
Year dc:date.issued
2016

Author and committee

dc:creator, dc:contributor.*
Author dc:creator
  • Petre, Cristian
Advisor dc:contributor.advisor
  • Mohamed, Yasser (Civil and Environmental Engineering)

Subjects

dc:subject × 9

Rights

dc:rights
Statement dc:rights
  • This thesis is made available by the University of Alberta Libraries with permission of the copyright owner solely for non-commercial purposes. This thesis, or any portion thereof, may not otherwise be copied or reproduced without the written consent of the copyright owner, except to the extent permitted by Canadian copyright law.
Language dc:language.iso
en

Identifiers

dc:identifier.*
DOI dc:identifier.doi
https://doi.org/10.7939/R39Z90P2N

Chain of custody

source
Harvested from
University of Alberta
Base URL
era.library.ualberta.ca/oai
Last updated
2026-11-26
Source record
OAI-PMH GetRecord
citation

Petre, Cristian. Instance-Based Model for Predicting Total Fabrication Duration of Industrial Pipe Spools. Master's thesis, University of Alberta, 2016. https://doi.org/10.7939/R39Z90P2N