Evaluating delays in execution of public sector construction projects : a study of roads and highways in Ghana

Abstract

dc:description.abstract

This study investigates delays in execution of public sector construction projects in Ghana. A review of literature revealed that previous studies on construction projects focused on cost, time overruns, as well as the causes of delays. It is against this background that this study assesses the causes and effects of construction project delays and means of averting such delays. The research design used in obtaining empirical data from a sample of 290 respondents was a survey research design. Questionnaires were used as instruments for data collection, and a Statistical Package for Social Sciences (SPSS) used for the data analysis. The statistical tools employed in the study include frequencies, percentages, Relative Importance Index (RII), Spearman correlation analysis and Chi-Square Test. The findings of the study revealed that some critical contributors to road construction project delay in Ghana during the project execution phase are clients' low cash flow to complete the project, contractors' financial constraints on the project, and improper planning of the project life cycle especially during the bidding phase. Site restriction, weather effects and changes in governmental regulations were found to be the least contributors to projects delays. These delays have a negative impact on project performance, project duration and force project participants to modify and adjust their finances. Investigating the way forward, the study explored strategies that are for averting the delays in executing construction projects. The study found that respondents were undecided in their rating on adequacy of training for project staff on specific requirements of construction projects. Other factors such as adequate of knowledge of contractors on project task, effective mobilization and release of resources, early engagement of project managers as well as adequate and effective supervision of construction activities were each identified as strategies that are applicable and feasible in averting the delays in executing road construction project activities.

Degree

thesis:*
Grantor dc:publisher.institution
Department of Mechanical Engineering
Year dc:date.issued
2016

Author and committee

dc:creator, dc:contributor.*
Author dc:creator
  • Narh, Natasha Afi
Advisors dc:contributor.advisor
  • Shaw, Corrinne
  • Windapo, Abimbola

Subjects

dc:subject × 1

Rights

Language dc:language.iso
eng

Identifiers

dc:identifier.*
Dc Identifier Apacitation
Narh, N. A. (2016). <i>Evaluating delays in execution of public sector construction projects : a study of roads and highways in Ghana</i>. (Thesis). University of Cape Town ,Faculty of Engineering & the Built Environment ,Department of Mechanical Engineering. Retrieved from http://hdl.handle.net/11427/20539
Dc Identifier Chicagocitation
Narh, Natasha Afi. <i>"Evaluating delays in execution of public sector construction projects : a study of roads and highways in Ghana."</i> Thesis., University of Cape Town ,Faculty of Engineering & the Built Environment ,Department of Mechanical Engineering, 2016. http://hdl.handle.net/11427/20539
Dc Identifier Citation
Narh, N. 2016. Evaluating delays in execution of public sector construction projects : a study of roads and highways in Ghana. University of Cape Town.
Dc Identifier Ris
TY - Thesis / Dissertation AU - Narh, Natasha Afi AB - This study investigates delays in execution of public sector construction projects in Ghana. A review of literature revealed that previous studies on construction projects focused on cost, time overruns, as well as the causes of delays. It is against this background that this study assesses the causes and effects of construction project delays and means of averting such delays. The research design used in obtaining empirical data from a sample of 290 respondents was a survey research design. Questionnaires were used as instruments for data collection, and a Statistical Package for Social Sciences (SPSS) used for the data analysis. The statistical tools employed in the study include frequencies, percentages, Relative Importance Index (RII), Spearman correlation analysis and Chi-Square Test. The findings of the study revealed that some critical contributors to road construction project delay in Ghana during the project execution phase are clients' low cash flow to complete the project, contractors' financial constraints on the project, and improper planning of the project life cycle especially during the bidding phase. Site restriction, weather effects and changes in governmental regulations were found to be the least contributors to projects delays. These delays have a negative impact on project performance, project duration and force project participants to modify and adjust their finances. Investigating the way forward, the study explored strategies that are for averting the delays in executing construction projects. The study found that respondents were undecided in their rating on adequacy of training for project staff on specific requirements of construction projects. Other factors such as adequate of knowledge of contractors on project task, effective mobilization and release of resources, early engagement of project managers as well as adequate and effective supervision of construction activities were each identified as strategies that are applicable and feasible in averting the delays in executing road construction project activities. DA - 2016 DB - OpenUCT DP - University of Cape Town LK - https://open.uct.ac.za PB - University of Cape Town PY - 2016 T1 - Evaluating delays in execution of public sector construction projects : a study of roads and highways in Ghana TI - Evaluating delays in execution of public sector construction projects : a study of roads and highways in Ghana UR - http://hdl.handle.net/11427/20539 ER -
Dc Identifier Vancouvercitation
Narh NA. Evaluating delays in execution of public sector construction projects : a study of roads and highways in Ghana. [Thesis]. University of Cape Town ,Faculty of Engineering & the Built Environment ,Department of Mechanical Engineering, 2016 [cited yyyy month dd]. Available from: http://hdl.handle.net/11427/20539

Chain of custody

source
Harvested from
University of Cape Town
Base URL
open.uct.ac.za/oai/request
Last updated
2026-11-27
Source record
OAI-PMH GetRecord
citation

Narh, Natasha Afi. Evaluating delays in execution of public sector construction projects : a study of roads and highways in Ghana. Department of Mechanical Engineering, 2016. https://hdl.handle.net/11427/20539