Determining preferred substation configurations based on reliability and cost

Abstract

dc:description.abstract

Many different substation configurations exist, each with its own space requirements, reliability and cost. Distribution planners need to choose between these numerous layouts and suggest the preferred substation configuration for future networks, but often don't understand the advantages and total life cycle cost associated with each. The aim of this research is to identify a simplified approach that can be used to determine a set of preferred substation configurations that minimises the total life cycle cost of the substation. An analytical approach is considered which uses deterministic reliability assessment to determine the load-based and economic performance indicators for different substation layouts. This analytical approach builds on the simplified reliability estimation approach developed by Van der Merwe (2014). This simplified approach is sufficiently complex to ensure that errors are not one-sided, while at the same time minimising the number of calculations of the reliability evaluation. A cost estimation tool was developed to determine the utility cost for each of the substations. The purpose of this tool is to prepare preliminary estimates of substation life cycle costs during the planning stage, based on conceptual design information. The value based reliability planning approach (VBRP) is used to determine the substation configuration with the lowest life cycle cost, given the specified design criteria. This substation is then the optimal configuration for the specific design criteria. The research considers 432 different substation configurations, and 720 different design criteria. This results in 311 040 different substation layouts. The approach was programmed into an MS Excel model and this model was used to compare the 432 different substation configurations for each of the 720 different design criteria and 18 different customer damage functions, i.e. repeating the comparison of the 432 different substations 12 960 times. The time required to perform one comparison of the 432 different substation configurations for one given design criteria and customer damage function is approximately 2 seconds. The process was automated and the time required to run through all the design criteria and customer damage functions was 8 hours 46 minutes on a standard laptop with an i5 processor. The optimal substation configuration obtained for each of the 12 960 scenarios were analysed and clustered in order to derive the preferred set of substation configurations. Through this process the 432 different substation configurations were reduced to only 17 different substation configurations.

Degree

thesis:*
Grantor dc:publisher.institution
Department of Electrical Engineering
Year dc:date.issued
2016

Author and committee

dc:creator, dc:contributor.*
Author dc:creator
  • Van der Merwe, Johanette
Advisor dc:contributor.advisor
  • Gaunt, C Trevor

Subjects

dc:subject × 1

Rights

Language dc:language.iso
eng

Identifiers

dc:identifier.*
Dc Identifier Apacitation
Van der Merwe, J. (2016). <i>Determining preferred substation configurations based on reliability and cost</i>. (Thesis). University of Cape Town ,Faculty of Engineering & the Built Environment ,Department of Electrical Engineering. Retrieved from http://hdl.handle.net/11427/20914
Dc Identifier Chicagocitation
Van der Merwe, Johanette. <i>"Determining preferred substation configurations based on reliability and cost."</i> Thesis., University of Cape Town ,Faculty of Engineering & the Built Environment ,Department of Electrical Engineering, 2016. http://hdl.handle.net/11427/20914
Dc Identifier Citation
Van der Merwe, J. 2016. Determining preferred substation configurations based on reliability and cost. University of Cape Town.
Dc Identifier Ris
TY - Thesis / Dissertation AU - Van der Merwe, Johanette AB - Many different substation configurations exist, each with its own space requirements, reliability and cost. Distribution planners need to choose between these numerous layouts and suggest the preferred substation configuration for future networks, but often don't understand the advantages and total life cycle cost associated with each. The aim of this research is to identify a simplified approach that can be used to determine a set of preferred substation configurations that minimises the total life cycle cost of the substation. An analytical approach is considered which uses deterministic reliability assessment to determine the load-based and economic performance indicators for different substation layouts. This analytical approach builds on the simplified reliability estimation approach developed by Van der Merwe (2014). This simplified approach is sufficiently complex to ensure that errors are not one-sided, while at the same time minimising the number of calculations of the reliability evaluation. A cost estimation tool was developed to determine the utility cost for each of the substations. The purpose of this tool is to prepare preliminary estimates of substation life cycle costs during the planning stage, based on conceptual design information. The value based reliability planning approach (VBRP) is used to determine the substation configuration with the lowest life cycle cost, given the specified design criteria. This substation is then the optimal configuration for the specific design criteria. The research considers 432 different substation configurations, and 720 different design criteria. This results in 311 040 different substation layouts. The approach was programmed into an MS Excel model and this model was used to compare the 432 different substation configurations for each of the 720 different design criteria and 18 different customer damage functions, i.e. repeating the comparison of the 432 different substations 12 960 times. The time required to perform one comparison of the 432 different substation configurations for one given design criteria and customer damage function is approximately 2 seconds. The process was automated and the time required to run through all the design criteria and customer damage functions was 8 hours 46 minutes on a standard laptop with an i5 processor. The optimal substation configuration obtained for each of the 12 960 scenarios were analysed and clustered in order to derive the preferred set of substation configurations. Through this process the 432 different substation configurations were reduced to only 17 different substation configurations. DA - 2016 DB - OpenUCT DP - University of Cape Town LK - https://open.uct.ac.za PB - University of Cape Town PY - 2016 T1 - Determining preferred substation configurations based on reliability and cost TI - Determining preferred substation configurations based on reliability and cost UR - http://hdl.handle.net/11427/20914 ER -
Dc Identifier Vancouvercitation
Van der Merwe J. Determining preferred substation configurations based on reliability and cost. [Thesis]. University of Cape Town ,Faculty of Engineering & the Built Environment ,Department of Electrical Engineering, 2016 [cited yyyy month dd]. Available from: http://hdl.handle.net/11427/20914

Chain of custody

source
Harvested from
University of Cape Town
Base URL
open.uct.ac.za/oai/request
Last updated
2026-11-25
Source record
OAI-PMH GetRecord
citation

Van der Merwe, Johanette. Determining preferred substation configurations based on reliability and cost. Department of Electrical Engineering, 2016. https://hdl.handle.net/11427/20914