Optimum time to refurbish a boiler feed pump at Eskom's power stations

Abstract

dc:description.abstract

A key focus area in power generation today is to improve equipment and plant efficiency, with this study specifically aimed to determine the optimum time to refurbish a boiler feed pump by analysing the internal wear of the annular seals. The boiler feed pump (BFP) installed in a power station is either driven by a steam turbine or an electric motor and the BFP is the highest auxiliary power consumer within the power station. In the 13 Eskom generating fossil fired power stations the installed BFPs consume approximately 1000 MWs of auxiliary power continuously. The focus of the study is to understand how the BFPs efficiency changes with time as a result of increased internal clearances and the effect this has on the auxiliary power consumption. An in-depth analysis of the efficiency degradation has been studied to understand the contributing factors to these changes and specifically the change in leakage rate and friction in the annular seals of the impellers and axial thrust balancing devices.

Degree

thesis:*
Grantor dc:publisher.institution
Department of Mechanical Engineering
Year dc:date.issued
2014

Author and committee

dc:creator, dc:contributor.*
Author dc:creator
  • Mortlock, Steven Peter
Advisor dc:contributor.advisor
  • Vicatos, George

Rights

Language dc:language.iso
eng

Identifiers

dc:identifier.*
Dc Identifier Apacitation
Mortlock, S. P. (2014). <i>Optimum time to refurbish a boiler feed pump at Eskom's power stations</i>. (Thesis). University of Cape Town ,Faculty of Engineering & the Built Environment ,Department of Mechanical Engineering. Retrieved from http://hdl.handle.net/11427/8704
Dc Identifier Chicagocitation
Mortlock, Steven Peter. <i>"Optimum time to refurbish a boiler feed pump at Eskom's power stations."</i> Thesis., University of Cape Town ,Faculty of Engineering & the Built Environment ,Department of Mechanical Engineering, 2014. http://hdl.handle.net/11427/8704
Dc Identifier Citation
Mortlock, S. 2014. Optimum time to refurbish a boiler feed pump at Eskom's power stations. University of Cape Town.
Dc Identifier Ris
TY - Thesis / Dissertation AU - Mortlock, Steven Peter AB - A key focus area in power generation today is to improve equipment and plant efficiency, with this study specifically aimed to determine the optimum time to refurbish a boiler feed pump by analysing the internal wear of the annular seals. The boiler feed pump (BFP) installed in a power station is either driven by a steam turbine or an electric motor and the BFP is the highest auxiliary power consumer within the power station. In the 13 Eskom generating fossil fired power stations the installed BFPs consume approximately 1000 MWs of auxiliary power continuously. The focus of the study is to understand how the BFPs efficiency changes with time as a result of increased internal clearances and the effect this has on the auxiliary power consumption. An in-depth analysis of the efficiency degradation has been studied to understand the contributing factors to these changes and specifically the change in leakage rate and friction in the annular seals of the impellers and axial thrust balancing devices. DA - 2014 DB - OpenUCT DP - University of Cape Town LK - https://open.uct.ac.za PB - University of Cape Town PY - 2014 T1 - Optimum time to refurbish a boiler feed pump at Eskom's power stations TI - Optimum time to refurbish a boiler feed pump at Eskom's power stations UR - http://hdl.handle.net/11427/8704 ER -
Dc Identifier Vancouvercitation
Mortlock SP. Optimum time to refurbish a boiler feed pump at Eskom's power stations. [Thesis]. University of Cape Town ,Faculty of Engineering & the Built Environment ,Department of Mechanical Engineering, 2014 [cited yyyy month dd]. Available from: http://hdl.handle.net/11427/8704

Chain of custody

source
Harvested from
University of Cape Town
Base URL
open.uct.ac.za/oai/request
Last updated
2026-11-20
Source record
OAI-PMH GetRecord
related terms
citation

Mortlock, Steven Peter. Optimum time to refurbish a boiler feed pump at Eskom's power stations. Department of Mechanical Engineering, 2014. https://hdl.handle.net/11427/8704