Executive (In) Decision? Explaining Delays in Canada's Defence Procurement System, 2006-2015

Abstract

dc:description.abstract

This dissertation asks how delays in Canada's defence procurement system can be explained. In answering this question, the hypothesis tested is that of the 'political executive'; the political body composed of the prime minister, cabinet and their advisors who sit at the apex of the federal government. With final decision-making powers over defence policy and budgets, the political executive has been inferred in existing scholarship as a decisive factor in delaying Major Crown Projects (MCPs) from moving through the procurement process but this has never been the subject to a scholarly analysis. Three other independent variables commonly identified in the literature as causing procurement delays were tested alongside the political executive: (1) the defence procurement bureaucracy; (2) the defence industry; (3) and Canada's military alliances and involvement in the Afghanistan war (2001-2014). Delays are treated as the dependent variable and are defined as a MCP not meeting its original planned project milestone dates. The dissertation relied upon four case studies in performing this analysis: The Joint Support Ships, the Medium Support Vehicle System - Standard Military Patter trucks, the Fixed-Wing Search and Rescue aircraft, and the Halifax-class Modernization/Frigate Life Extension. All four trace their beginnings to the Liberal governments of Jean Chrétien (1993-2003) and Paul Martin (2003-2006), but it was under the Stephen Harper Conservative government (2006-2015) that all were adopted into that government's procurement plans and it is in this period where delays occurred, for the first three case studies, and where apparent success was established with the fourth, the Halifax-class Modernization. (The first three case studies all experienced delays and are anywhere from seven to fourteen years behind their original schedule.) Relying upon process-tracing and the bureaucratic politics framework, this research concluded with a hypothesis not completely proven: the political executive can partly account for delays by not establishing clear policy guidance and governance models before a MCP reaches the project definition stage; however, a complete accounting for procurement delays is not possible without factoring in at least one the three independent variables, especially the defence procurement bureaucracy.

Degree

thesis:*
Name thesis:degree_name
Doctor of Philosophy (Ph.D.)
Level thesis:degree_level
Doctoral
Discipline thesis:degree_discipline
Political Science
Grantor dc:publisher
Carleton University
Year dc:date.issued
2018

Author and committee

dc:creator, dc:contributor.*
Author dc:creator
  • Collins, Jeffrey

Subjects

dc:subject × 1

Rights

dc:rights
Statement dc:rights
  • Copyright © 2018 the author(s). Theses may be used for non-commercial research, educational, or related academic purposes only. Such uses include personal study, research, scholarship, and teaching. Theses may only be shared by linking to Carleton University Institutional Repository and no part may be used without proper attribution to the author. No part may be used for commercial purposes directly or indirectly via a for-profit platform; no adaptation or derivative works are permitted without consent from the copyright owner.
Language dc:language.iso
en

Identifiers

dc:identifier.*

Chain of custody

source
Harvested from
Carleton University
Base URL
carleton.scholaris.ca/server/oai/request
Last updated
2026-11-19
Source record
OAI-PMH GetRecord
citation

Collins, Jeffrey. Executive (In) Decision? Explaining Delays in Canada's Defence Procurement System, 2006-2015. Doctoral thesis, Carleton University, 2018. https://hdl.handle.net/20.500.14718/38758