National Technical University of Athens (NTUA)
Χρονικός και οικονομικός προγραμματισμός έργων και χαρτοφυλακίων με ασαφείς περιορισμούς
Abstract
dc:descriptionScheduling and financial planning is hindered when it is based on fuzzy data. Thus, the validity of the main estimates, such as completion time, final cost and the expected cash flow is seriously affected. Moreover, projects are implemented in regard to time and cost constraints, the values of which cannot be precisely defined because of their intrinsic fuzziness. Therefore, the margin for improvement should be investigated, so that the scheduling and financial planning in regard to fuzzy constraints becomes more reliable and realistic.This Doctoral Thesis is aimed at investigating the importance and influence of Fuzzy Set Theory in scheduling and financial planning. Furthermore, it aims at developing a multi-level approach to the analysis and processing of scheduling and financial planning data in different management levels, i.e., project activities, projects, portfolios of projects and programmes of projects. Finally, the determination of the degree of fuzziness of the data that is necessary for scheduling and financial planning isinvestigated.The starting point of the research was to identify the margin for improvement in terms of dealing with fuzziness in existing scheduling and financial planning methodologies. To this end, a literature review and an evaluation of research efforts and practices in this field was conducted. Essentially, theThesis adapts elements of Fuzzy Set Theory to existing methodologies in order to model fuzziness. Finally, a software application was developed in the MATLAB computer programming environment for the implementation of new algorithms and the presentation of the results of the proposedmethodologies. The Thesis attempts to combine the duration and cost estimates, while there is also a uniform approach to the analysis and processing of data at different levels of detail. Specifically:i) At the project activity level, a methodology is presented for the estimation of the fuzzy duration and cost of activities.ii) In the special case of linear and repetitive projects the Fuzzy-Repetitive Scheduling Model (FRSM) was developed. In terms of the financial planning of projects, the concept of the S-Surface waspresented.iii) At the level of the portfolios of projects, the focus is on optimizing the use of shared resources with resource leveling techniques and heuristic algorithms.iv) At the level of programmes of projects, the impacts of fuzziness of individual projects on the cost and duration of the entire programme are examined. Additionally, elements from the scientific area of project cost-benefit analysis are combined with the theory of programme benefits management.The findings of the Thesis may be used collectively or individually in order to assist in scheduling and financial planning. Project managers can implement a methodology in one or several levels. New concepts that contribute to the development of scientific knowledge in scheduling and financial planning were developed. Finally, because the proposed methodologies are similar with existing scheduling and planning techniques, they could potentially be rapidly integrated within many practical applications.
Degree
thesis:*- Grantor dc:publisher
- National Technical University of Athens (NTUA)
- Year dc:date
- 2016
Author and committee
dc:creator, dc:contributor.*- Authors dc:creator
-
- Maravas, Alexander-Panayiotis
- Μαράβας, Αλέξανδρος-Παναγιώτης
Subjects
dc:subject × 16- Ασαφής χρονικός προγραμματισμός
- ΘΕΩΡΙΑ ΑΣΑΦΩΝ ΣΥΝΟΛΩΝ
- Χρηματορή έργου
- Καμπύλη-S
- Επιφάνεια-S
- Διαχείριση τεχνικών έργων
- Fuzzy project scheduling
- Fuzzy set theory
- Project cash flow
- S-curve
- S-surface
- Construction management
- Επιστήμες Μηχανικού και Τεχνολογία
- Επιστήμη Πολιτικού Μηχανικού
- Engineering and Technology
- Civil Engineering
Rights
- Language dc:language
- gre
Identifiers
dc:identifier.*- Identifier
- 10.12681/eadd/38805