Cost estimation of large construction projects with dependent risks: a study on the Brenner Base Tunnel

Abstract

dc:description

The realisation of large infrastructure projects appears as a challenging venture, not only from a technical point of view, but also in terms of methodical and effective cost evaluation. Moreover, numerous decisions throughout the phases of planning and construction, as well as during the project's service life, are firmly related to efforts to prevent, mitigate or address possible adverse events. The twofold requirement to quantify subjective perceptions of risks and to elaborate the resulting data in a mathematically consistent manner, may prove to be extremely demanding. The scope of the present study is to investigate, compare and propose methods for efficient acquisition and utilisation of information regarding risk and cost, in long-term and large-scale tunnelling projects. The developed methods should facilitate incorporating information, or lack thereof, into the risk analysis, in order to effectively treat uncertainty and to support decision-making. Also, they should be able to assist practitioners in aggregating all underlying risks and chances, so as to to solve a complex multi-dimensional problem, such as the estimation of the total cost. In particular, the present work focuses on the realistic representation of risk factors as individual cost elements and, consequently, on the formulation of a transparent computational setup, wherein these elements can be efficiently combined in order to yield reliable total cost estimates. Emphasis is drawn on quantitative decision-making under the-commonly encountered in singular undertakings-conditions of high uncertainty, complexity and partial information. The total cost is not viewed as a mere sum of fixed and independent values, but rather as the outcome of a stochastic framework, where risk fluctuations and dependencies are also considered. The conceptual model is inspired from and applied to the risk analysis of the Brenner Base Tunnel, one of the most important engineering projects being constructed nowadays in Europe.

Degree

thesis:*
Grantor dc:publisher
Institutes outside Greece
Year dc:date
2013

Author and committee

dc:creator, dc:contributor.*
Authors dc:creator
  • Tamparopoulos, Evripidis-Alexios
  • Ταμπαρόπουλος, Ευριπίδης-Αλέξιος

Subjects

dc:subject × 16

Rights

Language dc:language
eng

Identifiers

dc:identifier.*
Identifier
10.12681/eadd/60671

Chain of custody

source
Harvested from
Greek National Archive of PhD Theses
Base URL
phdtheses.ekt.gr/eadd_oai/request
Last updated
2026-11-18
Source record
OAI-PMH GetRecord
citation

Tamparopoulos, Evripidis-Alexios; Ταμπαρόπουλος, Ευριπίδης-Αλέξιος. Cost estimation of large construction projects with dependent risks: a study on the Brenner Base Tunnel. Institutes outside Greece, 2013. http://hdl.handle.net/10442/hedi/60671