Use of UHPC piles in integral abutment bridges

Abstract

dc:description.abstract

<p>In order to make the Ultra High Performance Concrete (UHPC) pile, developed in Phase I of the UHPC Pile Project at Iowa State University (ISU), a viable option in practice, laboratory testing, field testing and installation of a production pile in the field were undertaken during Phase II of this project. A detailed understanding of the section behavior and lateral loading behavior was determined and compared to that of a steal HP 10 x 57 pile through lateral load analyses of a UHPC pile section. The analysis found that UHPC piles were suitable for integral abutments of bridges.</p> <p>To make the field installation of UHPC piles possible, the overall performance of a common pile-to-abutment connection was verified in the laboratory by defining the UHPC pile-to-abutment connection, which is similar to the currently used connection for steel HP 10 x 57 piles. Both piles performances were verified by testing their connection when subjected to weak-axis bending. The test piles met performance criteria during the laboratory displacements of 0.28 and 0.42 inches which correspond to 1.0 and 1.55 inches in the field.</p> <p>Next, the field testing began to ensure that the production pile would achieve the desired behavior and capacities required by integral abutment bridges. A vertical load test on a 46-ft UHPC test pile was completed one week after being driven into the ground at the same site where the UHPC production pile was implemented into a 223-ft long integral bridge with a 24¢ª skew. Before failure, the test pile resisted 1.5 times the predicted capacity based on the Iowa Bluebook method of design for concrete piles, verifying appropriateness of reducing the UHPC production pile by 16% in length compared to the specified length of 65-ft for the HP 10 x 57 piles on the integral bridge.</p> <p>Additionally, a lateral load test was conducted between the second test pile with a newly designed splice detail and the vertical load test pile, which confirmed the adequacy of the splice detail and the lateral load resistance of the pile. The 46-ft test pile was also tested during the lateral load test. The results of the laboratory and field studies indicated that the UHPC pile in the field is a viable option.</p>

Degree

thesis:*
Name thesis:degree_name
Master of Science
Level thesis:degree_level
thesis
Department dc:contributor.department
Department of Civil, Construction and Environmental Engineering
Year dc:date.issued
2012

Author and committee

dc:creator, dc:contributor.*
Author dc:creator
  • Garder, Jessica
Advisor dc:contributor.advisor
  • Sri Sritharan

Rights

Language dc:language.iso
en

Identifiers

dc:identifier.*
Identifier
archive/lib.dr.iastate.edu/etd/12760/
Dc Identifier Other
3767
4186527
Mods Identifier Filename
archive/lib.dr.iastate.edu/etd/12760/Garder_iastate_0097M_13020.pdf|||Fri Jan 14 19:29:15 UTC 2022

Chain of custody

source
Harvested from
Iowa State University
Base URL
dr.lib.iastate.edu/server/oai/request
Last updated
2026-11-19
Source record
OAI-PMH GetRecord
related terms
citation

Garder, Jessica. Use of UHPC piles in integral abutment bridges. thesis thesis, 2012. https://doi.org/10.31274/etd-180810-1972