Schedule network node time distributions and arrow criticalities

Abstract

dc:description.abstract

<p>This research develops exact methods to calculate project duration distributions and to calculate Van Slyke's (1963) criticality for arrows, the probability that an arrow is on a critical path, assuming nonnegative integer duration distributions. These calculations for project duration distributions correct estimates made by the Program Evaluation and Review Technique (PERT), and the Van Slyke criticality calculations extend the arrow criticality analysis by the Critical Path Method (CPM) into the probabilistic realm;Exact methods for calculating project duration distributions and Van Slyke's criticality are demonstrated on series networks, parallel networks, parallel-series networks, and the Wheatstone network. The Van Slyke criticality equation for parallel networks is in a form that appears to improve upon one proposed by Dodin & Elmaghraby (1985). The present form is generalized to, in principle, include all networks;The exact methods are enhanced by developing a procedure to limit the number of calculations needed to analyze large networks. The procedure identifies paths through a large network, calculates the minimum and maximum path durations, and ranks the paths by duration. A smaller skeletal network is constructed from the arrows of the longest paths and is analyzed by exact methods. The procedure emphasizes accuracy for the longer project durations, of greatest concern to project managers and schedulers, while limiting the number of necessary calculations;The procedure for large networks is illustrated on the 40-arrow Kleindorfer (1971) network. Of the 51 Kleindorfer paths, the procedure selected 6 paths to construct a skeletal network. Analysis of the skeletal network yields a project duration distribution that is correct in its range and in the duration probabilities for the upper 5% of the distribution. Analysis results are compared with SLAM II and FORTRAN simulations. No arrow criticality appears to be seriously miscalculated. The project duration distribution is calculated to be bimodal, in keeping with the simulation;Conditions under which the just mentioned bimodality can occur are determined for parallel, normally-distributed paths. The large-network procedure warns when these oddly shaped distributions are possible.</p>

Degree

thesis:*
Name thesis:degree_name
Doctor of Philosophy
Level thesis:degree_level
dissertation
Department dc:contributor.department
Department of Industrial and Manufacturing Systems Engineering
Year dc:date.issued
1996

Author and committee

dc:creator, dc:contributor.*
Author dc:creator
  • Singleton, Scott
Advisor dc:contributor.advisor
  • H. T. David

Rights

Language dc:language.iso
en

Identifiers

dc:identifier.*
Identifier
archive/lib.dr.iastate.edu/rtd/11340/
Dc Identifier Other
12339
6453645
Mods Identifier Filename
archive/lib.dr.iastate.edu/rtd/11340/r_9626069.pdf|||Fri Jan 14 18:48:03 UTC 2022

Chain of custody

source
Harvested from
Iowa State University
Base URL
dr.lib.iastate.edu/server/oai/request
Last updated
2026-11-19
Source record
OAI-PMH GetRecord
related terms
citation

Singleton, Scott. Schedule network node time distributions and arrow criticalities. dissertation thesis, 1996. https://doi.org/10.31274/rtd-180813-10386