Scheduling based on earliness and tardiness criteria in assembly job shops

Abstract

dc:description.abstract

<p>In this research, the following four scheduling problems have been studied: (1) single machine problem with earliness cost minimization, (2) single machine problem with the sum of the weighted earliness and weighted tardiness cost minimization, (3) assembly job shop problem with earliness cost minimization, and (4) assembly job shop problem with the sum of weighted earliness and weighted tardiness cost minimization. Four mathematical models based on these four scheduling problems were developed in an effort to obtain optimal solutions. Six heuristic algorithms have been developed to solve the problems. The performances of the heuristic algorithms were demonstrated on some sample test problems. Quality of solutions and CPU time of solutions were the factors of interest. Several properties of optimal solutions for the single machine scheduling problem with the objective of minimizing the weighted earliness penalty have been identified in the research. Algorithms I, III, V, and VI were developed based on these identified properties while the algorithms II and IV were developed based on the tabu search concept;Algorithms I and II were developed to solve the first case (1) problem. The results indicate that these two algorithms are able to produce solutions close to optimal in small size problems. The results also show that algorithm I is relatively better than algorithm II in large size problem;Algorithms III and IV were developed to solve the second case (2) problem. Both algorithms obtained a small average deviation solutions (i.e., less than 2%) from optimal in small size test problems. For all problems tested, the algorithm IV is the best algorithm for solving the earliness/tardiness problems compared to algorithm III and the Ow & Morton algorithm;Algorithm V was developed to solve the third case (3) problem. It obtained an average deviation solutions less than 1% from the optimal. Algorithm VI was developed to solve the fourth case (4) problem. Algorithm VI obtained an average deviation solutions of 2.53% from the optimal;In testing all developed heuristics the computational requirements for solving the problems are less than 2 second in all test problems.</p>

Degree

thesis:*
Name thesis:degree_name
Doctor of Philosophy
Level thesis:degree_level
dissertation
Department dc:contributor.department
Department of Industrial and Manufacturing Systems Engineering
Year dc:date.issued
2000

Author and committee

dc:creator, dc:contributor.*
Author dc:creator
  • Pathumnakul, Supachai
Advisor dc:contributor.advisor
  • Pius J. Egbelu

Rights

Language dc:language.iso
en

Identifiers

dc:identifier.*
Identifier
archive/lib.dr.iastate.edu/rtd/12355/
Dc Identifier Other
13354
6784495
Mods Identifier Filename
archive/lib.dr.iastate.edu/rtd/12355/r_9990481.pdf|||Fri Jan 14 19:19:24 UTC 2022

Chain of custody

source
Harvested from
Iowa State University
Base URL
dr.lib.iastate.edu/server/oai/request
Last updated
2026-11-19
Source record
OAI-PMH GetRecord
related terms
citation

Pathumnakul, Supachai. Scheduling based on earliness and tardiness criteria in assembly job shops. dissertation thesis, 2000. https://doi.org/10.31274/rtd-180813-13624