Investigation of production and schedule improvement methods for urban interchange reconstruction projects

Abstract

dc:description.abstract

<p>This research was conducted to (1) analyze earthmoving productivity, (2) develop detailed schedules for urban interchange reconstruction for the Iowa Department of Transportation (Iowa DOT), and (3) determine whether expediting urban interchange construction is a possible solution for shortening duration for the reconstruction of Interstate 235 (I-235). The following projects were used as case studies in this research: (1) interchange reconstruction projects for the 14th Street, 19th Street, and 42nd Street in Des Moines, and 35th Street in West Des Moines. (2) bridge demolition projects for the 19th Street, Martin Luther King Street, and 42nd Street in Des Moines in the reconstruction of I-235. The analysis results based on site observation and statistical analysis were described in these case studies. In earthmoving analysis, factors influencing earthmoving production rates, such as bucket capacity, number of passes, and hauling distance in urban interchange construction were significant. For the scheduling part, the as-built schedules for 35 th Street in West Des Moines and 42nd Street in Des Moines were developed and compared with the contractor's original schedule. The actual urban interchange construction schedule resulted in a later completion date than originally estimated by the contractors. Even if earthwork, utility work, and paving processes were expedited based on the as-built schedules, the activities could be expedited aggressively to reduce the construction duration more. Expedited urban interchange construction is an alternative method to reduce total duration of the I-235 corridor work. Moreover, duration, costs, resources, and sequences for urban bridge demolition were influenced by traffic control and bridge type.</p>

Degree

thesis:*
Name thesis:degree_name
Master of Science
Level thesis:degree_level
thesis
Department dc:contributor.department
Department of Civil, Construction and Environmental Engineering
Year dc:date.issued
2004

Author and committee

dc:creator, dc:contributor.*
Author dc:creator
  • Kim, Seonghoon
Advisor dc:contributor.advisor
  • Charles T. Jahren

Rights

Language dc:language.iso
en

Identifiers

dc:identifier.*
Identifier
archive/lib.dr.iastate.edu/rtd/907/
Dc Identifier Other
1906
6087660
Mods Identifier Filename
archive/lib.dr.iastate.edu/rtd/907/1451877.PDF|||Sat Jan 15 02:27:46 UTC 2022

Chain of custody

source
Harvested from
Iowa State University
Base URL
dr.lib.iastate.edu/server/oai/request
Last updated
2026-11-19
Source record
OAI-PMH GetRecord
related terms
citation

Kim, Seonghoon. Investigation of production and schedule improvement methods for urban interchange reconstruction projects. thesis thesis, 2004. https://doi.org/10.31274/rtd-180813-125