A learning-based metaheuristic for multi-project scheduling in precast manufacturing: a case study of Singapore
Abstract
dc:description.abstractThe prefabrication of construction modules such as Prefabricated Bathroom Units (PBUs) requires the coordination of multiple projects that share limited factory resources. These projects involve many interdependent activities and must often be completed within strict delivery deadlines. This situation creates what is known as the Multi-Mode Resource-Constrained Multi- Project Scheduling Problem (MRCMPSP). In this problem, each activity can be executed in different modes, each with its own resource demands and durations, and the challenge lies in finding schedules that minimize the overall completion time while respecting resource limits and precedence relationships. This thesis introduces two hybrid optimization frameworks designed to address the MRCMPSP in the context of industrial prefabrication. The first contribution is a Learning-Enhanced Differential Evolution (LEDE) framework. It represents both the activity sequence and mode selection in a continuous form and evolves them together using features such as adaptive parameter control, strategy switching, elitism, and stagnation handling. By incorporating these mechanisms, the framework improves both global exploration and local refinement of schedules. Experiments with PBU production data show that LEDE outperforms traditional Genetic Algorithm (GA) and Differential Evolution (DE) methods in terms of makespan reduction and convergence speed, and it scales effectively to large problem sizes involving up to 100 PBUs. The second contribution builds on this foundation by integrating policy-based reinforcement learning into the LEDE framework. In this hybrid approach, LEDE continues to optimize the sequence of activities, while a reinforcement learning policy network adaptively selects execution modes based on the evolving state of the schedule. This separation allows the mode-selection process to learn from feedback and improve over time, while the evolutionary search explores alternative sequencing strategies. Results demonstrate that the combined LEDE + RL framework achieves better solution quality than either LEDE or RL alone, and adapts well to different levels of resource availability and project scales. The findings of this research provide both theoretical insights and practical implications. They show that combining evolutionary algorithms with learning-based methods can significantly improve scheduling performance in modular construction. The proposed frameworks not only advance the study of the MRCMPSP but also offer tools that can be extended to realworld prefabrication environments where flexibility, scalability, and adaptability are crucial.
Degree
thesis:*- College dc:contributor.school
- School of Civil and Environmental Engineering
- Grantor dc:publisher
- Nanyang Technological University
- Year dc:date.issued
- 2026
Author and committee
dc:creator, dc:contributor.*- Author dc:creator
-
- Xing, Zijie
- Advisors dc:contributor.supervisor
-
- Tiong Lee Kong, Robert
- Yang Yaowen
Subjects
dc:subject × 1Rights
dc:rights- Statement dc:rights
-
- This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License (CC BY-NC 4.0).
- Language dc:language.iso
- en
Identifiers
dc:identifier.*- Identifier URI
- https://hdl.handle.net/10356/214924