Factors leading to delays in construction in infrastructure based projects

Abstract

dc:description.abstract

The report describes an analysis programme conducted on road and infrastructure projects in Singapore. A survey was conducted on a sample of Project Management and Contract Administration individuals from various project teams to determine the factors affecting construction delays and their influence to the overall project duration. 'Multiple Regression' techniques were used to quantify the influence of independent variables that contribute to overall delays in construction. '

Author and committee

dc:creator, dc:contributor.*
Author dc:creator
  • Tong, Tee Hui.
Advisor dc:contributor.supervisor
  • Chen, Po-Han

Subjects

dc:subject × 1

Rights

dc:rights
Statement dc:rights
  • Nanyang Technological University

Identifiers

dc:identifier.*
Handle dc:identifier.uri
https://hdl.handle.net/10356/6607

Chain of custody

source
Harvested from
Nanyang Technological University
Base URL
dr.ntu.edu.sg/oai/request
Last updated
2026-11-27
Source record
OAI-PMH GetRecord
citation

Tong, Tee Hui.. Factors leading to delays in construction in infrastructure based projects. 2003. https://hdl.handle.net/10356/6607