An heuristic scheduling algorithm for resource-constrained project networks.
Abstract
dc:description.abstractAn algorithm is proposed for scheduling project networks having a single constraining resource and a constant level of available resources. The algorithm seeks to generate a minimum length schedule indirectly by maximizing the average resource utilization over the two time intervals represented by the current decision point and its successor. An attempt is made to schedule all of the activities whose predecessors have been completed, failing this all feasible subsets are considered. Where possible, the algorithm considers only those subsets which introduce new activities at the subsequent decision point.
Degree
thesis:*- Name thesis:degree_name
- M.S. in Operations Research
- Level thesis:degree_level
- Masters
- Discipline thesis:degree_discipline
- Operations Research
- Department dc:contributor.department
- Operations Research
- Grantor dc:publisher
- Monterey, California. Naval Postgraduate School
- Year dc:date.issued
- 1976
Author and committee
dc:creator, dc:contributor.*- Author dc:creator
-
- Marsh, Stewart Iden Jr.
- Advisor dc:contributor.advisor
-
- McMasters, Alan W.
- Committee member dc:contributor.committeemember
-
- Howard, G.T.
Rights
dc:rights- Statement dc:rights
-
- This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.
- Approved for public release; distribution is unlimited.
Identifiers
dc:identifier.*- Handle dc:identifier.uri
- https://hdl.handle.net/10945/17793