A case study on pile relaxation in dilative silts

Abstract

dc:description.abstract

In the mid-1980s the Jamestown Verrazzano Bridge was built in Rhode Island spanning the west passage of Narragansett Bay. The bridge was to be founded primarily on pre-stressed concrete piles acting as friction piles. A test pile program was conducted at the beginning of construction and the measured capacity of the piles was significantly lower than predicted values. This led to significant delays in construction, cost overruns, and ultimately led to a change in the design of the foundations. The overall objective of this thesis is to evaluate the results of the test pile program and attempt to understand why the measured capacities were so much lower than design values.

Degree

thesis:*
Name thesis:degree_name
Master of Science in Ocean Engineering
Level thesis:degree_level
Masters
Department dc:contributor.department
Ocean Engineering
Grantor dc:publisher
University of Rhode Island
Year dc:date.issued
2011

Author and committee

dc:creator, dc:contributor.*
Author dc:creator
  • Richardson, Brent D.

Rights

dc:rights
Statement dc:rights
  • This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.

Identifiers

dc:identifier.*
Handle dc:identifier.uri
https://hdl.handle.net/10945/24357

Chain of custody

source
Harvested from
Naval Postgraduate School
Base URL
calhoun.nps.edu/server/oai/request
Last updated
2026-11-19
Source record
OAI-PMH GetRecord
related terms
citation

Richardson, Brent D.. A case study on pile relaxation in dilative silts. Masters thesis, University of Rhode Island, 2011. https://hdl.handle.net/10945/24357