Using Fuzzy Mathematical Models for construction project scheduling with time, cost and material restrictions
Abstract
dc:description<p>This research investigation evaluated the viability of using fuzzy mathematical models for determining the duration of construction schedules and for evaluating the contingencies created by schedule compression and delays due to unforeseen material shortages. The research also used heuristic material allocation and sensitivity analysis to test five cases of material constraints. Material constraints increase the cost of construction and delay the finish of projects. Mathematical models allow the multiobjective optimization of project schedules, considering constraints such as time and cost defined in the project, and unexpected materials shortages to determine the fuzzy aspiration levels of Decision Makers.</p>
Degree
thesis:*- Name thesis:degree_name
- Master of Science (MS)
- Level thesis:degree_level
- masters
- Discipline thesis:degree_discipline
- Civil Engineering (Engineering)
- Grantor dc:publisher
- Ohio University
- Year dc:date
- 2007
Author and committee
dc:creator, dc:contributor.*- Author dc:creator
-
- Gonzalez, Julian Santiago, Sr.
- Advisor dc:contributor.advisor
-
- YATES, JANET
Subjects
dc:subject × 2Rights
dc:rights- Statement dc:rights
-
- unrestricted
- This thesis or dissertation is protected by copyright: all rights reserved. It may not be copied or redistributed beyond the terms of applicable copyright laws.
- Language dc:language
- English
Identifiers
dc:identifier.*- Repository record dc:identifier
- http://rave.ohiolink.edu/etdc/view?acc_num=ohiou1180987976