An information-based decision making framework for evaluation and forecasting a project cost and completion date

Abstract

dc:description

In the past, construction projects have frequently exceeded their cost and schedule resulting in financial losses to the owners; at present there are very few methods available to accurately predict an expected cost and completion date. These may be because of unforeseen outcomes that could not have been accounted for earlier and because of deficiency of proper tools to forecast the future status. To overcome these difficulties, project managers need a systematic and comprehensive decision making framework to pursue the successful achievement of projects’ goals within cost and on time. The main objective is to develop an information-based tool for evaluating and forecasting a project cost and completion during the execution. The research focuses on the construction phase of a project and is intended for the implementations by project managers. This research proposed a cost estimating model incorporating the Multivariate Probabilistic Analysis (MPA) developed to predict potential cost overrun and to quantify the uncertainty on an expected project cost. Bayesian Inference was employed to forecast project progress and completion date at the early stages as well as all construction stages. These proposed information-based tools address the effects of an informed data of completed work packages on the re-estimates of incomplete work packages, and assesses the impacts of a reported progress data on the variation of uncertainties on the forecasted completion date. The information-based decision making framework proposed in this research was developed for effective project control in quantitative and objective assessments. This framework is unique in the sense that it deals with the behavior of uncertainties and the impacts of an informed data on the expected final cost and completion date. Accordingly, this research offers an efficient framework to assist project managers’ improved management strategies. Actual projects are applied to demonstrate and illustrate the capabilities.

Degree

thesis:*
Name thesis:degree_name
Doctor of Philosophy
Level thesis:degree_level
doctoral
Discipline thesis:degree_discipline
Civil Engineering
Grantor dc:publisher
The Ohio State University
Year dc:date
2007

Author and committee

dc:creator, dc:contributor.*
Author dc:creator
  • Yoo, Wi Sung
Advisor dc:contributor.advisor
  • Hadipriono Tan, Fabian

Subjects

dc:subject × 1

Rights

dc:rights
Statement dc:rights
  • unrestricted
  • This thesis or dissertation is protected by copyright: all rights reserved. It may not be copied or redistributed beyond the terms of applicable copyright laws.
Language dc:language
English

Identifiers

dc:identifier.*

Chain of custody

source
Harvested from
OhioLINK
Base URL
etd.ohiolink.edu/acprod/odb_etd/ws/oai/oai
Last updated
2026-11-27
Source record
OAI-PMH GetRecord
citation

Yoo, Wi Sung. An information-based decision making framework for evaluation and forecasting a project cost and completion date. doctoral thesis, The Ohio State University, 2007. http://rave.ohiolink.edu/etdc/view?acc_num=osu1186596671