Abstract
dc:descriptionState Departments of Transportation are considering the use of accelerated construction techniques as a means of reducing traffic congestion during construction. Such techniques may cost more and DOT engineers must justify the increased cost through comparison to user costs. However, in order to determine the cost increase and the time saved in construction (a component of user cost), it is necessary to know the cost and time duration of non-accelerated projects. A benchmarking study is done to determine these values for box girder bridges. This study concludes that the cost of a box girder bridge is approximately $100 +/- $40/ square foot and the construction duration is approximately 120 days +/- 40 days. However, no correlation is found between cost and any other parameter of the bridge nor is there any correlation between construction time and any other bridge parameter.
Degree
thesis:*- Name thesis:degree_name
- MS
- Level thesis:degree_level
- masters
- Discipline thesis:degree_discipline
- Engineering : Civil Engineering
- Grantor dc:publisher
- University of Cincinnati
- Year dc:date
- 2007
Author and committee
dc:creator, dc:contributor.*- Author dc:creator
-
- STONE, ANDREA
- Advisor dc:contributor.advisor
-
- Miller, Dr. Richard
Subjects
dc:subject × 1Rights
dc:rights- Statement dc:rights
-
- unrestricted
- This thesis or dissertation is protected by copyright: all rights reserved. It may not be copied or redistributed beyond the terms of applicable copyright laws.
- Language dc:language
- English
Identifiers
dc:identifier.*- Repository record dc:identifier
- http://rave.ohiolink.edu/etdc/view?acc_num=ucin1186761137