Linear scheduling of pipeline construction projects with varying production rates
Abstract
dc:description.abstractScope and Method of Study: The purpose of this research was to expand the capabilities of linear scheduling to account for varying production rates in pipeline construction when and where they occur. This new linear scheduling model, Linear Scheduling Model with Varying Production Rates (LSM VPR) had two objectives. The first of these objectives was to outline a framework to apply changes in production rates when and where they occur along the horizontal alignment of the project. The second objective was to illustrate the difficulty or ease of construction through the time-location chart.
Degree
thesis:*- Discipline thesis:degree_discipline
- Civil Engineering
- Grantor
- Oklahoma State University
- Year dc:date.issued
- 2009
Author and committee
dc:creator, dc:contributor.*- Author dc:creator
-
- Duffy, Gregory Arthur
- Advisor dc:contributor.advisor
-
- Oberlender, Garold D.
- Committee members dc:contributor.committeemember
-
- Ahmed, Mohamed Samir
- Jeong, Hyung S.
- Hobson, Dana E.
Rights
dc:rights.accessrights- Statement dc:rights.accessrights
-
- Open Access
- Copyright is held by the author who has granted the Oklahoma State University Library the non-exclusive right to share this material in its institutional repository. Contact Digital Library Services at lib-dls@okstate.edu or 405-744-9161 for the permission policy on the use, reproduction or distribution of this material.
- Language dc:language
- en_US
Identifiers
dc:identifier.*- Mods Identifier Filename
- Duffy_okstate_0664D_10198.pdf