Examining opportunities to improve the pre-construction schedule performance of Seattle Public Utilities scope in Seattle Department of Transportation capital projects

Abstract

dc:description.abstract

This study discerns and analyzes opportunities to improve the schedule performance of the City of Seattle’s water, sewer, and drainage improvements that are delivered through transportation capital projects. This issue is particularly salient, as Seattle’s water, sewer, and garbage ratepayers are spending over $100 million each year on capital improvements that are a result of unprecedented transportation construction – which inevitably creates impacts and opportunities to below-grade infrastructure. This research takes the form of a multi-case descriptive study, examining three projects with significant utility scope that was delivered through transportation contracts. Specifically, this thesis focuses on schedule performance during the initiation, options analysis, and design phases of the project delivery lifecycle. As a result, this research found misaligned production systems between the utility and transportation agencies, as well as divergent policy drivers and mental models that reinforce the status quo. These findings and the following recommendation are derived from semi-structured interviews with project team members, observation of project delivery processes and artifacts, and pertinent theories, empirics, and literatures of practice. A recommendation to implement lean production – or a continuous improvement culture based on front-line empowerment and eliminating waste – is put forward from a limited policy analysis.

Author and committee

dc:creator, dc:contributor.*
Author dc:creator
  • Herrera, Marlon Dylan
Advisors dc:contributor.advisor
  • Whittington, Janice
  • Herranz, Joaquín

Subjects

dc:subject × 9

Rights

dc:rights
Statement dc:rights
  • CC BY
Language dc:language.iso
en_US

Identifiers

dc:identifier.*
Handle dc:identifier.uri
http://hdl.handle.net/1773/43166

Chain of custody

source
Harvested from
University of Washington
Base URL
digital.lib.washington.edu/server/oai/request
Last updated
2026-11-18
Source record
OAI-PMH GetRecord
citation

Herrera, Marlon Dylan. Examining opportunities to improve the pre-construction schedule performance of Seattle Public Utilities scope in Seattle Department of Transportation capital projects. 2018. http://hdl.handle.net/1773/43166