Determination of project duration for resource constrained projects without using resource scheduling procedure

Abstract

dc:description.abstract

<p>The problem addressed in this thesis is that of determining the practicability of equating measures of network and resource characteristics to the early finish date of a project which is constrained by resources. The output of standard critical path calculations along with information on resource profiles that are easy to calculate can be of use in estimating resource constrained project duration.</p><p>Twenty two different equations ( developed by Hall) were used to find the estimated project finish dates. These results were compared to the schedule resulting from the application of the heuristic rule of minimum activity float. It is shown that the calculations may be used as a substitute to resource leveling procedure.</p>

Degree

thesis:*
Name thesis:degree_name
Master of Science in Civil Engineering - (M.S.)
Discipline thesis:degree_discipline
Civil and Environmental Engineering

Author and committee

dc:creator, dc:contributor.*
Author dc:creator
  • Karmakar, Rabindra Nath
Contributors dc:contributor
  • Edward G. Dauenheimer
  • Walter Konon
  • John R. Schuring

Subjects

dc:subject × 3

Identifiers

dc:identifier.*
Repository record dc:identifier
https://digitalcommons.njit.edu/theses/3112

Chain of custody

source
Harvested from
NJIT
Base URL
digitalcommons.njit.edu/do/oai/
Last updated
2026-11-19
Source record
OAI-PMH GetRecord
citation

Karmakar, Rabindra Nath. Determination of project duration for resource constrained projects without using resource scheduling procedure. https://digitalcommons.njit.edu/theses/3112