Spelling suggestions: "subject:"alectric power systems."" "subject:"delectric power systems.""
401 |
Contingency severity analysis using linearized flow bound estimates : theory and numerical experienceCheng, John Wing Mao. January 1984 (has links)
No description available.
|
402 |
Un système expert pour la gestion en temps réel des alarmes dans un réseau électrique /Girouard, Pierre January 1987 (has links)
No description available.
|
403 |
Elektros energijos gamybos valdymas restruktūrizuotose elektros energetikos sistemose / Electrical energy generation control in restructured power systemsBikulčius, Ramūnas 19 July 2005 (has links)
Purpose of this work is to propose and study new ways of automatic generation control (AGC) and ways for accounting of this service; formulate key methodology principles of payment for system services; estimate costs of automatic generation control.
|
404 |
A knowledge-based model and simulator for alarm and protection systems of power networks /Arès, Jean-Michel January 1987 (has links)
No description available.
|
405 |
Derivation and applications of optimum bus incremental costsPonrajah, Ranendra Anthony. January 1984 (has links)
No description available.
|
406 |
The use of surge arresters in parallel for the lightning protection of pole mounted distribution transformers in Eskom.Chatterton, Baden George. January 2002 (has links)
Eskom (Electricity Supply Commission of South Africa) is the national electrical utility that provides the generation, transmission and distribution of electricity in South Africa. The majority of Eskom's electricity distribution is done with either 11 kV or 22kV electrical overhead networks. An unacceptable number of Eskom's pole mounted power transformers on these networks have been failing over the past six years in the Kwa-Zulu Natal region. The average transformer failure rate for the Distribution Eastern Region was calculated to be 2.4% per annum. International norms seem to indicate a transformer failure rate of between 0.5% and 1.0% per annum as acceptable. The estimated cost of these transformer failures was between R9 million and R13 million per annum for the Eastern Region. Eskom Distribution has seven regions and the total cost of these failures was considerable to the business. These transformer failures contributed an average of 5.3% per month of the Supply Loss Index (SLI) for the Eastern Region, with a maximum contribution of 14.5% per month of the SLI for the region. The SLI is an Eskom performance measure of the unavailability of supply of the networks. The Eskom plant performance database (NAPI) was statistically analysed in detail and a number of field investigations conducted at transformer installations that had failed in the past. Transformer earth electrode resistance measurements were taken in an attempt to identify the cause of these transformer failures. Local transformer manufacturers were consulted and a national transformer refurbishment company's database was analysed during the investigation as part of a holistic approach to the industry related dissertation. The main finding of the NAPI data analysis was that the majority of the transformers failed during lightning storm periods. Another similar Eskom investigation had a sample of failed transformers opened for internal inspection. Signs of lightning damage to either the primary side winding or the primary lead were found. The proposed failure hypothesis was that the transformers required additional lightning protection of the primary side to protect the transformer against lightning. It seemed that the current specification of the Eskom distribution class surge arresters was inadequate to offer sufficient lightning protection of the pole mounted transformers. Practical measures were implemented on existing Eskom 11 kV networks in the Glencoe area as part of an Eskom research project to reduce the high failure rates of transformers. Two experimental networks were established and one control network was used as a reference line. The project implementation was completed at the end of October 1999. The experimental project looked at applying additional primary side lightning protection of the transformers. The main emphasis of the lightning protection on the first network was the use of two distribution class arresters in parallel (double arrester configuration) for each transformer and an understrung conductor connected to the prior structure back from the transformer installation. The second network had the standard single arresters installed on the transformers. A 600mm wood path was placed in series with an earthed down conductor installed on each intermediate woodpole structure to ensure a basic insulation level of 300kV for the network. The control network also had single arresters installed and was a fully insulated network (no earthed down conductor on the woodpoles). Each network was carefully monitored in terms of equipment failures and the performance levels of each network was measured with installed voltage dip recorders near the individual network circuit breakers. The Eskom Lightning Position and Tracking System (LPATS) data was collected and analysed to quantify the lightning activity before the project implementation to that of after project implementation. For the period November 1999 to March 2002 not a single transformer or surge arrester had failed ,due to lightning on the double arrester and understrung conductor configuration experimental network. There were recorded transformer and surge arrester failures on the second experimental network and on the control network. It was found that the practical methods implemented on the networks did not have a negative impact on the performance levels of the networks. Laboratory work was conducted in the high voltage laboratory at the University of Natal, on various metal oxide varistor (MOV) blocks of opened up new and failed surge arresters. This was to determine the effect of MOV blocks in parallel under power frequency and current impulse conditions. In particular, to determine what the effect of parallel MOV blocks with different voltage-current (V-I) characteristics would have on the current sharing and energy absorption capabilities of the individual blocks. The work was performed to simulate the behaviour of two surge arresters in parallel as in the experimental project. The experimental project lines were modeled using the Alternative Transients Program (ATP) simulation package and various parametric studies performed in the single phase conductor simulations. Each network component (such as the line, transformer and surge arrester) and phenomena (such as the effect of corona, the transient earth electrode resistance and voltage flashover) were modeled. The effect of surge arresters in parallel and the use of an understrung conductor arrangement were quantified. A current sharing factor (k-factor) was introduced to quantify the sharing of currents through surge arresters in parallel with different V-I curves. The main finding from the impulse laboratory work was that current sharing between parallel MOV blocks became better at higher currents. This finding was supported by other research work findings, particularly in the field of nuclear fusion research with parallel arresters. The results of the ATP simulations showed that the experimental network with the parallel arresters and understrung conductor arrangement considerably reduced the energy absorbed by the individual arresters. The effect of the double arrester configuration was to reduce the energy absorbed by the individual arresters even with arresters with different V-I characteristics and different manufacturers. The understrung conductor arrangement was found to be the major contributor towards the reduction of the energy absorbed by the arresters. The equivalent circuit of a MOV block for transient studies was proposed and then simulated in ATP. The simulated results were compared to the measured waveforms obtained from the impulse laboratory work. A good agreement between the simulated and measured waveforms was obtained. For existing Eskom networks with high arrester and transformer failure rates, the double arrester (distribution class) configuration would be the most time and cost effective solution. The alternative of using a single station class arrester is not proposed due to the costs involved and the availability of stock. The understrung conductor arrangement did significantly reduce the energy absorbed by the arresters but due to high labour costs and time requirements this would not be recommended for existing networks. It is suggested that Eskom investigate this practical method for new lines to be built in high lightning areas. Even with arresters from different manufacturers, the use of the double arrester configuration would decrease the energy absorbed and hence reduce the risk of failure of the individual arresters protecting the transformer. This means that Eskom field staff can use different manufacturer arresters in parallel. This would be especially for times when replacing failed arresters or a faulty transformer under breakdown conditions and electrical supply has to be restored to the customer as soon as possible. It was proposed to perform arrester matching by ensuring that the both arresters were from the same manufacturer. / Thesis (M.Sc.Eng)-University of Natal, Durban, 2002.
|
407 |
Robust power system stabilizer design.Moodley, Devandren. January 2002 (has links)
This thesis investigates the design of damping controllers to alleviate the problem of
low frequency electro-mechanical oscillations in power systems. The operating point
and network parameters of power systems are continually changing, resulting in
changes in system dynamics. The conventional controller design methodology has
therefore come under increasing scrutiny for its lack of considerations for robustness.
The thesis first outlines the conventional design of a power system stabilizer (PSS) and
then applies two robust techniques (Hoo and Quantitative Feedback Theory, QFT) to the
design problem. The single machine infinite bus (SMIB) model is used to illustrate the
procedure for all three design techniques. The final design is undertaken to illustrate the
more important problem of robust multi-machine PSS design using QFT. The design
requires linearised models of the multi-machine system. A brief discussion is given on
how these can be obtained. An introduction to decentralized control design in QFT is
included to support the multi-machine design.
Chapter three proceeds through the design steps required to generate a conventional
PSS. The technique is shown to be simple for a given set of operating conditions. The
controller is shown to be adequately robust over the given set of operating conditions
albeit not by design.
Chapter four introduces a design technique that directly addresses robustness issues
during the controller design. For a restricted range of operating conditions the designed
controller demonstrates the desired robustness and performance characteristics. The
inherent difficulties with Hoo in PSS design become more apparent as the operating
range is extended.
Chapter five introduces the second robust controller design technique. QFT is shown to
be more adept at dealing with increased operating ranges and changing specifications in the single-machine infinite-bus case. The controller is easy to generate and performs
well over the entire range of operating conditions. QFT is also applied to the controller
design for a four-machine study system. The design is a marginally more complex than
in the single machine case but is still easily accomplished.
This thesis confirms previous attempts at solving the design problem using the methods
outlined above. The performance of all controllers is assessed for small and large
disturbances using non-linear time domain simulations with models developed using
PSCAD/EMTDC and MATLAB. / Thesis (M.Sc.)-University of Natal,Durban, 2002.
|
408 |
The application of controllable inverter-based series compensation to power oscillation damping.Chonco, Nkosinathi Stanford. January 2000 (has links)
Poorly damped oscillations that occur between the generators in large interconnected
power systems often limit the amount of power that can be transmitted through a
transmission corridor and are a threat to secure system operation. Coordinated
insertion and removal of capacitors in series with a transmission line is one of the
approaches that has been known for many years to be capable of enhancing the
damping of power system oscillations. Unfortunately however, this approach
historically relied on the operation of mechanical circuit breakers which were too
slow and unreliable for the high-speed and repetitive operation that such an
application demands. Recently-emerged, high-speed power-electronic-based
switching devices are finding increasing use in modem power systems in the so-called
Flexible AC Transmission Systems (F ACTS) concept. One particular FACTS
impedance controller, namely the inverter-based series compensator, can rapidly alter
the magnitude of capacitive compensating reactance in series with the line to make it
practically feasible to enhance the damping of power system oscillations via
dynamically-controlled series compensation.
This thesis identifies, in the literature, an insightful approach to the design of an
idealised controllable series compensator (CSC) damping scheme; such an approach
has been considered in the analyses of the thesis. Three mathematical models of a
single-machine infinite bus (SMIB) system are developed and are subsequently used
in the initial design and analysis of a CSC damping controller carried out in the thesis.
The simple SMIB system case study is used to identify and investigate the factors that
have a significant impact on the performance of a CSC damping controller before
studying the more complex issue of inter-area mode damping using a CSC.
This thesis successfully confirms the results of a previous analytical study in which an
idealised representation of the CSC was used, and extends the scope of that previous
study by also considering a detailed representation of one particular type of CSC: the
inverter-based series compensator. The two key findings of this extended
investigation are that the inverter-based form of controllable series compensator can
successfully be used to damp power oscillations and that, where the damping of oscillations is the particular focus of study, an idealised representation of the inverterbased
CSC is suitable for the analyses.
In the case of the inter-area mode damping problem, the selection of an appropriate
input signal to the CSC damping controller is a key issue, since the oscillations that
are to be damped involve a number of participating generators. This thesis examines
the suitability of a few candidate input signals that have been proposed in the
literature using the conceptually simpler SMIB system analytical models that have
been developed. Finally, the thesis applies the understanding of CSC damping
controller design gained from the SMIB study to the problem of inter-area mode
damping on a four-generator study system. Time-domain simulation results are
presented to demonstrate the impact of the controlled inverter-based series
compensator on the damping of the inter-area mode of this system. / Thesis (M.Sc.Eng.)-University of Natal, Durban, 2000.
|
409 |
An investigation into the feasibility of migrating from PILC to XLPE as the cable technology of choice for medium voltage electricitiy networks in South Africa.Ryan, Morgan. January 2011 (has links)
South African medium voltage underground electrical networks consist mainly of cables of
paper insulated lead covered construction. This construction is still the standard used for most
utilities in South Africa. While the in-service performance history of these cables has been
excellent, global manufacture of this cable type is decreasing.
Internationally, the use of polymeric cables is increasing, resulting in the security of the supply
chain for paper cable becoming an increasingly important issue. The most widely used
polymeric construction is cross-linked polyethylene. Modern distribution switchgear, which is
increasingly used in South Africa, is designed for the newer polymeric technology as this
enables more compact construction and reduced equipment footprint. The reduced clearances
present installation and operational issues when using modern switchgear with paper insulated
cables.
Although a comprehensive literature review was conducted, not much academic work has been
done on the process of migrating from one cable platform to another. Manufacturer data,
academic reference sources, industry experts and software modelling tools are used to
demonstrate that the use of polymeric technology is viable for South African utilities.
This dissertation focuses on the difference between paper and polymeric technologies, and
explores the advantages and disadvantages of each. Integration issues are examined along with
the methods used to overcome the challenges of hybrid or mixed dielectric networks. Economic
comparisons between paper and polymeric cables with respect to purchase and operating costs
(including the cost of losses) as well as steady state, cyclic, distribution and emergency current
ratings are made.
The dissertation concludes that it makes economic and engineering sense for users of paper
cable in South Africa to change to polymeric technology, taking the recommendations given
into consideration in order to choose an optimised cable design and gain maximum benefit from
the change. / Thesis (M.Sc.Eng.)-University of KwaZulu-Natal, Durban, 2011.
|
410 |
Model enhancements for state estimation in electric power systemsHansen, Charles William 12 1900 (has links)
No description available.
|
Page generated in 0.0888 seconds