Using a Duration-Based Schedule Performance Index to Monitor the Performance of Projects Including Estimating the Final Cost

Abstract

dc:description.abstract

One of the main concerns of project managers is monitoring the schedule performance of construction projects. A project manager needs tools to not only understand the status of project schedule performance, but also to find the causes of delays and the corresponding corrective actions. Hence, discovering time deviations from the project plan provides more reliable project schedule control. Applying statistical quality control charts on the project schedule performance index is suggested in this study. The use of quality control charts in this research monitors the process plan and provides first alarms for applying changes by detecting the time deviations over the project duration. For the schedule performance, Earned Value Management (EVM) has been shown to be a very powerful tool. However, EVM calculations are monetary based, which provides some misleading results for measuring the duration of the project. Earned Duration Management (EDM) introduces a better metric for schedule performance that solves this illusory results of EVM by detecting cost and schedule performance measures. So, applying statistical quality control charts on the EDM's schedule performance index is recommended in this research. Moreover, because of changes to tasks to correct project delays, it becomes more difficult to estimate the final budget. So in this study, considering the time value of money, delay in employer payment and contractor cash flow in different phases of the construction projects, beside the use of EDM schedule index is suggested to calculate the final budget of the project. A construction case study illustrates the enhancement of the introduced method.

Degree

thesis:*
Name thesis:degree_name
MS
Level thesis:degree_level
Thesis
Discipline thesis:degree_discipline
Industrial and Managements Systems Engineering

Author and committee

dc:creator, dc:contributor.*
Author dc:creator
  • Yousefi, Nooshin
Contributors dc:contributor
  • Kenneth Currie
  • Majid Jaridi
  • Feng Yang

Identifiers

dc:identifier.*

Chain of custody

source
Harvested from
West Virginia University
Base URL
researchrepository.wvu.edu/do/oai/
Last updated
2026-11-19
Source record
OAI-PMH GetRecord
related terms
citation

Yousefi, Nooshin. Using a Duration-Based Schedule Performance Index to Monitor the Performance of Projects Including Estimating the Final Cost. Thesis thesis, https://doi.org/10.33915/etd.7015