驅逐黑暗、迎來光明,是變電所最重要的任務,但它往往被歸類為鄰避設施,不為使用者所接受。變電所引發的風險疑慮,無論是環境、健康等,儘管尚無法以科學實證其因果關係,卻深深烙印人心;加上不甚透明且缺乏參與機制的規劃方式,致使變電所選址過程抗爭不斷。
現代社會可說是充滿風險的社會,也就是德國學者貝克所謂的「風險社會」。風險不分階級、貧富,充斥在我們身旁,引發無聲且無形的恐懼。高科技雖然帶來生活便利,但也帶來前所未有的新風險—科技風險。既然風險是現代社會非常重要且切身的課題,如何以風險的視角來解構變電所選址過程,便成為本文的論述主軸。
現行變電所用地之規劃方式,主要是依據都市計畫(土地使用管制)及電力負載預測結果來選擇變電所設置地點;變電所用地的使用項目與內容,則取決於是否辦理多目標使用。然而,土地使用管制之僵固性及電力負載預測結果的不確定性卻造成變電所選址過程必須面臨規劃方式、民眾抗爭、風險分配等三方面困境,使得變電所選址困難重重。
規劃部門、電力公司與民眾能否「共同面對」變電所選址在規劃方式、民眾抗爭、風險分配等三方面的困境,尋求變電所土地使用管制內容再定位並融合民眾參與機制(儘管民眾參與並非萬能),使變電所選址過程掙脫規劃方式的枷鎖,將是降低變電所選址抗爭且形成風險分配共識的必要方向,也才是風險社會中變電所選址的最佳出路。 / The primary function of a substation is to expel the darkness and usher in light. However, it is usually classified as NIMBY facilities and not welcomed by public.
People are constantly worried and even feared by nearby substations, although there is neither scientific evidence to prove that substations are harmful nor directly caused any disease. Moreover, substation siting procedure is less transparent and lack of participatory mechanisms during the planning stage, resulting in protests against substation during the siting process.
Modern society is full of risks as described by German sociologist Dr. Ulrich Beck in “Risk society.” Risks are around us all the times, regardless of class or wealth. It creates silent and invisible fears. Modern high-tech life style provides convenience but technology also brings unprecedented new risks - technological risks. Since technological risk is an important issue and it can affect anyone in modern society, this article will discuss the risks involved by deconstructing the substation siting procedure.
The existing substation siting models are based on the designation of urban plan and the results of power load forecast; the land-use projects of substation are depended on the content of multi-objective land-use. The rigidity of zoning and the uncertainty of power load forecast results plight in substation siting procedure at three situations: approach to planning, public protests and risk allocation, also makes substation siting much difficult.
Although public participation is not the magic bullet, substation siting zoning restriction can be unlocked by combining public participation with land use re-position. The best approach to prevent protest against substation siting process and reach consensus in risk distribution is to have planning departments, power companies and the community seeking solution together.
Identifer | oai:union.ndltd.org:CHENGCHI/G0093923015 |
Creators | 黃宇賢, Huang, Yu Hsien |
Publisher | 國立政治大學 |
Source Sets | National Chengchi University Libraries |
Language | 中文 |
Detected Language | English |
Type | text |
Rights | Copyright © nccu library on behalf of the copyright holders |
Page generated in 0.0017 seconds